Top management has accepted the schedule created at the end of Part. Prepare a brief memo that addresses the following questions:

1. How much will the project cost? What is the most expensive activity?

2. What does the cash flow statement tell you about how costs are distributed over the life span of the project?

Include a monthly cash flow for the project.

Once you are confident that you have the final schedule, save the file as a baseline.
Hint: Save a backup file just in case without baseline!

Part 2:

Part A

Today's date is July 8, 2015, the milestone date for the completion of the Prototype. You are charged with preparing a status report for top management. Table A2.8 summarizes progress on the Red Zuma project:

TABLE: Red Zuma Project Update

 

Task Name

Act. Start

Act. Finish

% Comp.

Phys. % Comp.

Act. Dur.

Rem. Dur.

1

1 Red Zuma

Fri 1/9/15

NA

46%

0%

125.85 days

146.4 days

2

 1.1 Market Analysis

Fri 1/9/15

Thu 2/12/15

100%

0%

25 days

0 days

3

 1.2 Product Design

Fri 2/13/15

Wed 4/1/15

100%

0%

35 days

0 days

4

 1.3 Manufacturing Study

Fri 2/13/15

Fri 3/6/15

100%

0%

16 days

0 days

5

 1.4 Product Design Selection

Thu 4/2/15

Fri 4/17/15

100%

0%

13 days

0 days

6

 1.5 Detailed Marketing Plan

NA

NA

0%

0%

0 days

15 days

7

 1.6 Manufacturing Process

NA

NA

0%

0%

0 days

30 days

8

 1.7 Detailed Product Design

Mon 4/20/15

Wed 6/24/15

100%

0%

49 days

0 days

9

 1.8 Build Prototypes

Wed 6/10/15

NA

39%

0%

9 days

14 days

10

 1.9 Lab Test Prototypes

NA

NA

0%

0%

0 days

10 days

11

 1.10 Field Test Prototypes

NA

NA

0%

0%

0 days

15 days

12

 1.11 Finalized Product Design

NA

NA

0%

0%

0 days

20 days

13

 1.12 Final Manufacturing Process

NA

NA

0%

0%

0 days

10 days

14

 1.13 Order Components

NA

NA

0%

0%

0 days

7 days

15

 1.14 Order Production Equipment

NA

NA

0%

0%

0 days

14 days

16

 1.15 Install Production Equipment

NA

NA

0%

0%

0 days

35 days

17

 1.16 Celebrate

NA

NA

0%

0%

0 days

1 days

Submit a professional status report to Robin Lane that addresses the following questions:

1. How is the project progressing in terms of cost and schedule?

2. What activities have gone well? What activities have not gone well?

3. How much of the project has been accomplished (PCIB)?

4. What is the forecasted cost at completion (EACf)?

5. What is the estimated completion date?

6. How is the project doing in terms of priorities (see Part 1)?

Report and interpret relevant Earned Value metrics in your report.

Include a Tracking Gantt chart as well as an Earned Value Table with your memo.

Part B

You have told Robin Lane that based on what you know now you need to revise the estimates for some of the remaining activities. Detailed Product Design is expected to take 3 days longer than planned. Build Prototypes is expected to take 2 days less than planned and Finalized Product Design is expected to take 3 days longer than planned. Final Manufacturing Process is expected to take 2 days less than planned, while Install Production Equipment is now expected to take only 30 days.

You also report that Detailed Marketing plan will be completed before the end of the New Year. She is insisting that the project be completed by January 17th in order to be ready for the Las Vegas show. She is willing to spend $50,000 from Management Reserves to expedite shipping if necessary. $25,000 would reduce the shipping of components by 5 days and/or $25,000 would reduce the shipping of manufacturing parts by 5 days (Hint: Adjust lag).

Prepare a memo to Robin that addresses the following questions:

1. What is the impact of the revised estimates for Finalized Product Design and Install Production Equipment on the project schedule and cost?

2. Would you recommend authorizing the expenditure of $50,000? Explain.

3. What, if any other recommendations, would you make so that the project can achieve Robin's deadline? Justify your recommendations.
Include a Tracking Gantt chart with variance schedule that depicts your final recommendations and revised schedule.

Hint: After adjusting the Installation of Production Equipment and Finalized Product Design, level outside of slack to eliminate any resource over allocation problems.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91694894
  • Price:- $75

Priced at Now at $75, Verified Solution

Have any Question?


Related Questions in Project Management

This is the brief for the third and final exercise for this

This is the brief for the third and final exercise for this project. Your group has been appointed as Project Manager by The Proprietary Very Limited Corporation (PVLC) to carry out development and feasibility analyses o ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

How might researchers study the effectiveness of inclusive

How might researchers study the effectiveness of inclusive leadership with regard to overall organizational effectiveness and competitiveness?

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As