This part of the paper requires you to apply your understanding of project management as a whole through the following scenario.

Scenario

Assume you've started a small, one-person project management consulting firm. Your first two clients asked you similar but different questions. These two clients are friends with each other who want to see how you answer both of their questions. To this end, these clients requested-and you agreed-that you answer their questions by comparing and contrasting your recommendations for using project management in response to the following 2 questions.

Client # 1 (Jack): Do I need to bother with project management if I'm only going to build a single birdhouse to put in my backyard?

Client # 2 (Diane): Do I need to bother with project management if I'm only setting up an additional, new production line for a product we already produce?

Since your clients are busy, they asked-and you, once again, agreed-that your response not exceed 3 double-spaced pages which include any models, diagrams, and/or tables using a 12-point font and finch margins.

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam.

2. Second, answer your clients' question in the manner indicated in the above scenario.

3. Last, post your material using the appropriate link in Blackboard.

Part 2

A third client came to your consulting firm with a different request. Ms. Prynne's company charged her with determining the length of time a new project will take to complete and the "critical path" (which Ms. Prynne does not know what means) the project manager (aka Ms. Prynne) should watch carefully during the execution of the project.

Background

Ms. Prynne was promoted to be the project manager for a project that updates the baggage control system at the local airport. At the present time, Ms. Prynne is interested in learning more about project management and wants to learn the needed skills to properly conduct a time analysis. To this end, Ms. Prynne asked that you complete an AON diagram and accompanying data table which she will study and ask any questions necessary for clarification. The work package predecessors and duration estimates (given in weeks) as listed below are all the details Ms. Prynne has at the moment. [NOTE: This table is duplicated in the MS Excel spreadsheet which accompanies this exam.]

Exam

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam. 2. Second, perform the following tasks and answer the questions as appropriate. a. Open the Excel file named "Final Exam Part

2 start". b. On the one spreadsheet in this file, complete an Activity-on-Node network diagram which reflects the material in the "Data Table". c. Enter the correct information in the remaining columns in the Data Table. Below the Data Table, answer the following questions. d. What is the critical path? e. What is the projected length of the project (in weeks)? f. What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks? 3. Last, post your material using the appropriate link in Blackboard.

Work
Package

Predecessor

Duration
(in weeks)

A

--

2

B

A

2

C

A

3

D

A

4

E

B

2

F

C

3

G

D

6

1-1

E, F

2

I

E, F

5

J

G, I

1

K

H, J

2

Instructions

1. First, review the rubric for this part of the exam which is attached with the exam as well as included as part of the assignment for this part of the exam.

2. Second, perform the following tasks and answer the questions as appropriate.

a. Open the Excel file named "Final Exam Part 2 start".
b. On the one spreadsheet in this file, complete an Activity-on-Node network diagram which reflects the material in the "Data Table".
c. Enter the correct information in the remaining columns in the Data Table. Below the Data Table, answer the following questions.
d. What is the critical path?
e. What is the projected length of the project (in weeks)?
f. What is the impact on the project (and the project manager) of changing the duration of task H from 2 weeks to 6 weeks?

3. Last, post your material using the appropriate link in Blackboard.

Attachment:- Project_Part_2_Start.xlsx

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92059748

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As