On day 51 a project has the earned value of $600, the actual cost of $650, and planned cost of $560. find out the SV, CV, and CPI for project. Determine your assessment of project on day 51?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932666

Have any Question? 


Related Questions in Project Management

1 what is a line extension and how does it differ from a

1. What is a line extension, and how does it differ from a product modification? 2. Compare and contrast the three major approaches to modifying a product. 3. Identify and briefly explain the seven major phases of the ne ...

1 dollar for dollar with comparable characteristics which

1. Dollar for dollar with comparable characteristics, which is faster and more powerful-a desktop computer or a notebook computer? 2. What is the difference between vertical and horizontal market software?

Iexplore is an internet company that offers a variety of

iExplore is an Internet company that offers a variety of travel and adventure products. Visit its website at www.iexplore.com. a. Based on the information provided at the website, what are some of iExplore's basic produc ...

This assignment consists of two parts a project schedule

This assignment consists of two parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the ass ...

Using porter to evaluate the movie rental industry- one

USING PORTER TO EVALUATE THE MOVIE RENTAL INDUSTRY:- One hotly contested and highly competitive industry is the movie rental business. You can rent videos from local video rental stores, you can order pay-per-view from t ...

1 a company typically has many systems it wants to build

1. A company typically has many systems it wants to build, but unfortunately it usually doesn't have the resources to build all the systems. How does a company decide which systems to build? 2. How do the four implementa ...

What is planning how does an organization determine if

What is planning? How does an organization determine if planning is necessary? What are the three common levels of planning? Who are stakeholders? Why is it important to consider their views when planning? What is a valu ...

Consider that you work in the human resources management

Consider that you work in the human resources management department of a local business and that many of your friends work there. Although you don't personally generate payroll checks, you still have the ability to look ...

Assignmentscenarioyou work as a project manager for the it

Assignment Scenario You work as a project manager for the IT department at your company, a supplier of customized management software packages for the oil industry. Your company is in the process of a big expansion, and ...

Discussionproject scheduleto develop a schedule for a

DISCUSSION Project Schedule To develop a schedule for a project, we will use the concept of a project network, which shows work activities taken from the work breakdown structure and is organized according to the logical ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro