Associated Engineering conducted an evaluation of sources of water supply for a municipality. One of the considerations was the choice of high-pressure or conventional pipelines for transmitting treated water to the municipality from a distant water source. Conventional pipelines, most often made of concrete, have a limited maximum tensile strength, which for analysis purposes was taken to be 200 pounds per square inch (psi). High-pressure pipe, made of steel, can withstand up to 60 000 psi, although the pipe examined by Associated Engineering had a strength of 42 000 psi.

The major advantage of the steel pipe is that fewer pumping stations are needed than with the concrete pipe. The distance to be pumped is 85 kilometres; this requires either one pumping station for high-pressure pipe or six pumping stations for concrete pipe. Each pipeline type was analyzed over a range of pipeline diameters ranging from 24" to 72". Construction costs included the pipe, pumping stations, and a reception reservoir, with the time of the cost taken to be the commissioning date of 2025. Operating and maintenance costs starting in 2026 were included, and administration, engineering fees, contingencies, and taxes were also accounted for. The best alternative was chosen on the basis of a present worth comparison with a 4% discount rate. In the analysis, real 1993 dollars were used and an inflation rate of 2% was assumed for the period of study. The result was that a 360-diameter high-pressure pipeline was economically best, at a present cost S7.5 million lower than for the best conventional pipeline.

Discussion
Estimating future inflation is difficult. The average inflation in manv developed countries over the last 50 years has been about 4%, but there have been periods of several vears when it has been 2% to 2.5%. For some other periods, inflation has averaged over 10%. Historically, many countries have experienced hyperinflation (extreme inflation) or even deflation. How can we estimate future inflation? One way is simply to assume that inflation will remain at the current value. This is probably wrong; as has been seen, inflation typically changes over time.

However, there are factors that are controlling the inflation rate. Lacking knowledge of any reason why these controlling factors might change, the current rate seems to be a reasonable choice. A second approach is to use the long-term average. Knowing that inflation will change over time suggests that the long-term average is a good choice even if inflation is lower or higher than the average right now. After all, those controlling factors have changed in the past and are likely to change again.

A third way is to take into account the controlling factors for inflation. These include government policy: a government committed to social welfare is likelv to induce more inflation than one committed to fiscal responsibility. Trends in business and consumer behaviour affect inflation: large labour contract increases presage inflation, as does high consumer borrowing. Social trends like the aging of the baby boomers also have an effect on inflation. Understanding the effect of the controlling factors for inflation in detail is very difficult. So usually decision makers make a broad judgment based on both the current inflation rate and the historical average, and perhaps informed by a general understanding of the contributing factors.

Questions:
1. How significant would the difference have been to the savings of the high-pressure pipeline if an inflation rate of 4% had been used instead? -Assume the only difference between the concrete- and steel-pipe systems was the capital cost, expended in 2025. Would the decision be any different? Could it be different for any assumed inflation rate?

2. Design two cash flow structures for projects that start in 2025, such that the present worth in the current year at a discount rate of 4% is higher for one project than the other at an inflation rate of 2%, but lower at an inflation rate of 4%. Is there a significant opportunity to control the best choice in a decision situation by selecting the appropriate inflation rate?

3. Why would the analysts have chosen to separate the inflation rate from the discount rate for this problem, rather than combining them into an actual dollar discount rate? Do you think the analysts estimated the actual dollar cost of the alternatives in 2025, or would thev have used the real costs?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92184475

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As