Ask Question, Ask an Expert

+61-413 786 465

info@mywordsolution.com

Ask Project Management Expert

MINI-CASE :

The city of Hong Kong has a dense population with limited land suitable for housing. As a result, building trends have been toward taller apartment units, with many in excess of 140 m. With water resource management a large concern for city planners, the design of efficient building water supply systems is very important. A key component of the design process is estimating the maximum total simultaneous water demand in such buildings so that engineers can limit the water supply failure rate to less than 1%. The challenge for city engineers is to balance the cost of the water supply system with its reliability. A variety of methods have been used to estimate the maximum load. They typically involve using the flow rate of each water fixture, the number of water fixtures in a building, and an estimated parameter that captures the probability that all of the fixtures are in use simultaneously. These "fixture-unit" methods were initially developed in the mid-1900s, and were parameterized with empirical data from medium-rise housing. Hong Kong engineers were concerned that the methods might not be suitable for high-rise buildings.

To address this concern, the engineers conducted a survey of close to 600 households to find out the typical daily usage patterns of various water consuming appliances for each family member. Combining this with sampled flow rates and flow duration for each of the appliances, they were able to construct probabilitv distributions for each of these sources of variation. The engineers then used this information as input to a Monte Carlo simulation, which was used to construct a cumulative risk profile for the peak water load on the system. The simulation predicted a peak load of only 50%-60% of that computed by the "fixture-unit" method, and implied a much lower cost for the high-rise buildings' water supply system. These findings were thought to be useful in updating the methodology for computing water demand in high-rise residential construction and were seen to be a step forward in balancing cost with water supply reliabilitv.

Discussion
As a result of technological change and the emergence of new societal needs, engineers must constantly review and update design processes. In this mini-case, increases in the height of apartment towers and the need to better manage natural resources were the driving forces behind consideration of new design parameters for load estimation for sizing water plants and piping systems. The design parameters developed vears previously for low-rise or medium-rise buildings were not considered appropriate for the very highrise housing common in Hong Kong. Also, the need to manage fresh water consumption through the use of efficient water supply systems was considered necessary. The process of estimating overall peak water needs started with studying the individual components of an aparnnent water system-the typical domestic appliances one would find in an apartment.

By collecting data on the water consumption of each appliance, and then by sampling appliance usage patterns by time of day, day of week, and by time of year, the engineers were able to build up a profile for water usage patterns. The sampling allowed them to establish probability distributions for the number of users served by a particular appliance, the flow rate of an appliance, its operating time and the hourly use of the appliance. Using this as their basic unit of analysis, they could then build up a model of an apartment system by specifying its size, and how the individual components interacted.

For many engineering projects, system-level behaviour can be difficult to predict, even if there is a good model of how individual components behave. For example, in this mini-case, older peak water consumption models assumed that all appliances in the same washroom could be in use simultaneously. A more realistic assumption, validated by the interview results, was that only one could be in use at a time. While the older model might have been more mathematically tractable, the model developed in this mini-case allowed for more complex and realistic interactions. As a result, the engineers were able to produce a predictive model that met the needs of technological change and societal need.

Questions
1. Many projects can be implemented without an initial simulation study. Name a few examples, and explain why decisions about their acceptability can be made without a simulation study.

2. What are the characteristics of projects where simulation makes sense? Provide several examples of this type of project.

3. Simulations can help with evaluating different design alternatives, including the possibility of pinpointing potential problems. Can you think of other benefits provided by a simulation?

4. The output of a single simulation trial is a random variable. What is the problem with using only one trial for the purposes of decision making?

5. Ji-Ye is evaluating a proposal to build a plant that will cost 7670 000 000. A consultant has offered her a simulation that was developed to model the performance of a similar plant in the United States. If she wanted to use the American simulation, what considerations would she need to make for its application in a Chinese setting? How might she judge how much to spend on the simulation?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92185443

Have any Question?


Related Questions in Project Management

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

You are recently assigned to manage an effort to upgrade

You are recently assigned to manage an effort to upgrade about 200 desktops in your company to Windows 10. The project has 4 team members reporting directly to you and is estimated to last about 3 months. Per your compan ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

How can you assist in determining human resource

How can you assist in determining human resource requirements and How can you contribute to establishing and maintaining productive team relationships?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As