IS/IT Project Management-The critical path

Many project managers ensure the success of their projects by using the concept of a critical path to better plan and manage IS/IT projects.

In this Assignment, you will consider the following scenario:
You are managing an IS/IT project that is an upgrade to infrastructure of a customer relations management (CRM) tool. The work breakdown structure (WBS) of this upgrade exercise produces three major activities: the system memory upgrade, the system database upgrade and the Web interface upgrade.

There are five activities planned in this project, and their sequence has been determined:

  • The first activity is the completion of memory upgrade, which is planned to take two days.
  • The second activity is the system design rework, which is planned to take six days.
  • The third and fourth activities are separate activities and are planned to take 12 and four days, respectively, both requiring the system design rework as the input.
  • The last activity is the Web upgrade, which is planned to take 10 days of JavaScript work. The system memory upgrade, system database upgrade and Web interface upgrade are prerequisites for this activity.

You are given a team of three: one hardware specialist, one system and Web interface designer and one database developer. Each is a specialist in his or her own area only.

To complete this Assignment:
Submit a paper in which produce a task activity network for the project described and determine the critical path for this project. Critically analyze the critical path in relation to predicting a project completion activity date. Explain whether and why you would predict a completion date based on the critical path and discuss the alternatives that you have. Based on your analysis, evaluate the applicability of the concept of a critical path to this project.

Length :700+words.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92218185
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As