The project about building a network wireless for the company

This part follows on from the previous Grand Wines assignment case study. Now that the project sponsor has approved your Project Charter and associated documents, you may proceed to the planning phase of the project by providing a formal project report for the project sponsor based on the following project planning documents. You may make any appropriate assumptions needed to enable the successful completion of the project.

  • Project Time Management

- Gantt chart
- Identify at least eight milestones for this project using SMART criteria.
- Network Diagram (Critical path diagram)

  • Project Cost Management

- Resources table
- Project budget,The total cost for all the work and Materials are $150,000. Please make sure not to exceed this budget. You need to extract the budget from your Gantt chart.
- RACI Table

  • Project Risk Management

- Identify 6 potential risks for this project and write the risk register for all of them.  Ensure one of your risks is a positive risk.
- Construct the Probability/ Impact Matrix for those 6 potential risks.

Rationale

Marking criteria

Task 1

  • Gantt chart is Correct
  • Time allocated for each tasks and dependencies  given makes sense
  • Allocated resources for each tasks makes sense
  • No overload of any resources

Task 2

  • Milestones given makes sense
  • Correctly explained the milestones using SMART criteria
  • Quality of presentation of answers

Task 3

  • Critical path duration is realistic

Task 4

  • Project resource table is correct
  • Quality of presentation of answers

Task 5

  • Project budget is realistic
  • Quality of presentation of answers

Task 6

  • RACI table makes sense
  • Quality of presentation of answers

Task 7

  • Risk registers given are realistic
  • Risk register format is correct
  • Quality of presentation of answers

Task 8

  • Probability/ Impact scores makes sense
  • Probability/ Impact matrix is correct
  • Quality of presentation of answers

 

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9404815

Have any Question?


Related Questions in Project Management

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

Leading lean projects assessment case study - continuous

Leading Lean Projects Assessment Case study - Continuous Improvement Introduction - Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the t ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

How can you assist in determining human resource

How can you assist in determining human resource requirements and How can you contribute to establishing and maintaining productive team relationships?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As