Ask Project Management Expert

I am choosing the Project Proposal assignment for a system that will provide customer information on an Insurance Protection Program for phones. The stat date will be February 1, 2016 and the completion date will be December 31, 2016. The project will need 10 team members who have SQL database service experience. The determined budget will be 2.0 million dollars which I have included $500, 00 thousand for any hidden cost.

As you move forward with future assignments, all different components of the project are constructed leading to a final compilation, and presentation, of your project.hree to four (3-4) page paper in which you:

1. Propose a project idea, and explain a selection method for selecting the project (i.e., financial or non-financial method). Provide a rationale for your proposal.

2. Construct the objectives of the project in terms of a problem which it solves or an opportunity which it capitalizes on.

3. Create a scope statement (using the template on page 105 of the textbook) for your project. Make sure to include all necessary components of the scope statement.

Scope Statement below:

PROJECT OBJECTIVE: To implement a system that will provide customer information on an insurance Protection Program for devices by 12/31/2016

DELIVERABLES:

• Project Plan Proposal
• Analysis each phases to build functionality
• Design the Prototype
• Validation and Contraction of Prototype
• Training material and technical requirements
• UAT of the Business Validation of Packaged Release

MILESTONES

• Project Plan Proposal 02/1/2016
• Software Model 04/01/2016
• System Design (diagrams of sequences, components, DB Model) 06/01/2016
• System Prototype 08/01/2016
• Software development 09/01/2016
• UAT 10/01/2016 - 11/30/2016
• Launch Planning 11/01/2016
• Training material 11/01/2016
• Software Complete 12/01/2016

TECHINAL REQUIREMENTS

• Product perspective
 
System Interfaces
Hardware interfaces
Software interfaces
Communication Interfaces
Memory Constraints
Operations
Site Adaptation Requirements

o Product functions
o User characteristics
o Constraints, assumptions and dependencies

• Specific requirements

o External interface requirements
o Functional requirements
o Performance requirements
o Design constraints

Standards Compliance

o Logical database requirement
o Software System attributes

Reliability
Availability
Security
Maintainability
Portability

o Other requirements

LIMITS AND EXCLUSIONS

• The software will meet all requirement for End User Acceptance and meet all requirement for Data Security
• Training will be Train the Trainer
• Updates will be done nightly between 12AM and 6AM
• Upgrades will be scheduled

CUSTOMER REVIEW- Business Owners, Business Subject Matter Expert, End User.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91614959

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As