You are a general manager of the large construction project. Contract has both financial incentives for finishing on time or early also large penalties if project is completed late. To get project done on time or early that project planning using formal timeline is essential. You ask project manager to address following problems:

1. In terms of developing timeline, what do you mean by critical path of PERT chart?

2. As project manager you know that fastest possible time project can be completed is known as critical path. This implies that any delay in any step of projects critical path, will hence delay overall project. On a particular project, step B is part of critical path; step C and D both are not. Suppose that all of these steps, B, C, and D are at risk of being delayed due to some issue (could be lack of people, lack of materials, equipment downtime - it makes no difference).

How would manager go about prioritizing correction of problem existing in B, C, or D? Should manager address issue in step B first, step C first, or step D first; why?

3. Once repair is finished in step #2, how would go you about prioritizing repairs at other two steps?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932532

Have any Question? 


Related Questions in Project Management

Competing internationallywhen making purchasing decisions

Competing Internationally When making purchasing decisions, should a corporation reduce its ethical standards in order to allow the company to compete internationally? Take a position and defend your answer. REFERENCE Wi ...

Strategy management course- structure of the project report

Strategy Management course- Structure of the project report (for any international company) 1- Introduction of the company and mission, vision and corporate objectives (1 page) 2- SWOT Analysis: (strengths, weaknesses, o ...

Task - weightingyour team should consider a newactual

TASK - WEIGHTING Your team should consider a new(actual/ hypothetical) project. You have to develop a project management plan for the project selected by your group. Your project management plan report shall cover manage ...

Read the given article and provide a technical discussion

Read the given article and provide a technical discussion and critique of the ideas that are presented. You may use the following questions as prompts, but you are expected to explore the issues and concepts more fully. ...

Individual assignment risk driversrisk assessment and risk

Individual Assignment: Risk Drivers Risk assessment and risk management are used to identify and mitigate risk drivers. A risk driver is a situation in a project from which project risks can arise. Identifying risk drive ...

Develop and describe an entrepreneurial storyboard for a

Develop and describe an Entrepreneurial Storyboard for a current product on the market. Template will be provided with examples in class. Deliverables: The Storyboard will be presented in two forms: 1 One four-slide Powe ...

1 write short note ona pure project management

1. Write short note on: a. Pure project management organization b. Bottom-up approach for estimating project planning c. Project delays d. Partnering 2. Explain the analysis and evaluation phase of the project management ...

Taskpart oneproject name team descriptionworking as a

Task Part One: Project Name / Team / Description Working as a team you are to - Agree on a suitable team name, list all team members and provide their contact details in a professional looking document. - Provide an over ...

Your ceo is a visionary who wants you to transform the way

Your CEO is a visionary who wants you to transform the way the company conducts business. She is fascinated by computer software for project management and requires that you conduct a SWOT analysis of this service in rel ...

Change management communication and leadershipduring this

Change Management Communication and Leadership During this course, you have developed many of the artifacts utilized by project managers. You have learned that, contrary to common misconceptions, project managers are inv ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate