Ffollowing information for the one-year project, reply the following problems: Recall that PV is planned value, EV is earned value, AC is actual cost, and BAC is budget at completion. PV = $23,000; EV = $20,000; AC = $25,000; BAC - $120,000

Determine the cost performance index (CPI), cost variance, schedule variance, and schedule performance index (SPI) for project?

How is project doing? Is it ahead of schedule or behind schedule? Is it under budget or over budget?

Utilize CPI to compute estimate at completion (EAC) for this project. Is project performing better or worse than planned?

Use schedule performance index (SPI) to evaluate how long it will take to complete this project.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932327

Have any Question? 

Related Questions in Project Management

Write about yourself and how music relates to youwhat is

Write about yourself and how music relates to you. What is your musical background? How does music affect your life? What most interests you in taking this class? What most concerns you? 600 Words...........

Competing internationallywhen making purchasing decisions

Competing Internationally When making purchasing decisions, should a corporation reduce its ethical standards in order to allow the company to compete internationally? Take a position and defend your answer. REFERENCE Wi ...

Agile project managementproject title us homeland security

Agile Project Management Project Title: U.S. Homeland Security Biohazard Incident Tracking and Coordination System (BITCS). Brief Description: XYZ has just won a contract with the federal government to put in place a sta ...

Assignment project schedule changesyou have kicked off the

Assignment: Project Schedule Changes You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the ...

Assignment - reflection writingquestion 1in module 1 the

Assignment - Reflection Writing (Question 1): In Module 1, the first required assignment asked you to examine the course and relate it to a current, real-world event or recent news story. Based on what you have learned i ...

Case studyread the following scenario and answer the

Case Study Read the following scenario and answer the corresponding questions upon your completion. You recently earned your Project Management Professional (PMP) certification, and you are excited to share the news with ...

1 write short notes ona graphical evaluation and review

1. Write short notes on: a. Graphical Evaluation and Review Technique (GERT) b. Cost control 2. Describe CPM technique of project planning. 3. What do you understand by managing cash flow? 4. Describe how you can choose ...

What are the differences between a project operations and a

What are the differences between a project, operations, and a program? Please be sure to provide an example and justification for each. Your response should be at least 200 words in length.

Assessment 1 - project workpart aoverviewyou are required

ASSESSMENT 1 - PROJECT WORK Part A Overview You are required to develop a project management plans, for given scenarios. These project plans requires you to: - Implement start-up activities through updating and confirmin ...

Project deliverable project planthis assignment consists of

Project Deliverable: Project Plan This assignment consists of three sections: a written project plan, revised business requirements document, project plan PowerPoint presentation, and a finalized project plan. You must s ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate