U.S. Army Corps of Engineers has contracted with medium-size excavation firm to create small series of three earthen dams as part of flood control program in North Carolina. For economic reasons, dams #1 and #2 have to constructed at the same time and dam #3 can only be built after #1 and #2 are completed. There is also very significant scheduled completion date which has to be met (relating to next year's flood season). Project is being tackled by Bryan Johnson, who has been with company for about year.

This is new job for Bryan in that he had never before headed more than one project at time. About three months into building of dams #1 and #2, he started to notice the information problem. He had supervisors from dams #1 and #2 reporting to him, but he never know how far along they were in relation to each other. As dam #3 can't be made until both dams are fully complete, he can't tell if it will be started on time and hence completed on time. Realizing situation was becoming serious, he started to wonder about how he could coordinate projects. How could he tell where projects were in relation to each other? How far were they jointly behind? Bryan's main problem was his inability to monitor and record dual projects effectively.

What would you suggest to Bryan?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M933136

Have any Question? 


Related Questions in Project Management

Question 1eoq q radic219500254 49371 494

Question 1: EOQ = Q = √(2(19,500)(25))/4 = 493.71 = 494 units b) Annual holdings costs = [Q/2] H = [494/2](4) = $988 c) Annual ordering costs = [D/Q]S = [19500/494](25) = $987 Question 2:  a) EOQ = 2DS/H = 2 (250) 20/1 = ...

Fundamentals of project managementdefining the projectusing

Fundamentals of Project Management Defining the Project Using the South University Online Library or the Internet, research, select, and scope out any project of your choice. The project you select must meet the followin ...

1 write short note ona pure project management

1. Write short note on: a. Pure project management organization b. Bottom-up approach for estimating project planning c. Project delays d. Partnering 2. Explain the analysis and evaluation phase of the project management ...

Questionthis final research paper must demonstrate an

Question: This final research paper must demonstrate an understanding of new learning in logistics management and how the supply chain supports the organization's business strategy. The paper must be eight- to- ten pages ...

Cases and examplesastro bankthe management of the project

Cases and examples Astro Bank The management of the project teams for both the legacy and new systems started badly. Separate project teams were established for each. No roles, responsibilities, or rules were established ...

Project management- international project and project

Project Management- : International Project and Project Oversight The Project Management Maturity Model (PM3) is a model that allows us to describe our organization's functioning level related to Project Management pract ...

Assignment project schedule changesyou have kicked off the

Assignment: Project Schedule Changes You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits. You originally were told the ...

Project managementpreviously in the course you were asked

Project Management Previously in the course, you were asked to think of a project you have been involved with at your place of employment. Think of that same project, imagine that you have been appointed the project mana ...

Case study assignmentpurpose of the assessmentscope creep

Case Study Assignment Purpose of the assessment: Scope creep can occur when the scope of a project is not properly documented, defined, or controlled. It is generally considered a negative occurrence, and thus, should be ...

What are the differences between a project operations and a

What are the differences between a project, operations, and a program? Please be sure to provide an example and justification for each. Your response should be at least 200 words in length.

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate