General Instructions: Submit your answers on a separate sheet of paper and submit through Blackboard

1.

a. Find the schedule variance for a project that has an actual cost at month 22 of $540,000, a scheduled cost of $523,000, and an earned value of $535,000.

b. A project at month 5 had an actual cost of $34,000, a planned cost of $42,000, and value completed of $39,000. Find the schedule and cost variances.

c. A project at day 70 exhibits an actual cost of $78,000, a scheduled cost of $84,000, and a value completed of $81,000. Find the schedule and cost indices.

2.    Consider the information about a project plan in the following table.

Task

Immediate

Predecessor

Duration

Scheduled

Cost/Day

A

-

3

$1,000

B

-

5

$2,000

C

A

4

$4,000

D

B

7

$1,000

E

C

6

$2,000

F

D

8

$3,000

The following table shows the weekly control reports for the first two weeks (assume 5 working days each week).

 

End of Week 1

End of Week 2

Task

Actual %

Completed

Cumulative

Actual Cost

Actual %

Completed

Cumulative

Actual Cost

A

60%

$1,500

100%

$ 2,900

B

30%

$3,000

100%

$11,000

C

10%

$2,000

100%

$13,500

D

0%

$        0

90%

$10,000

E

0%

$        0

50%

$ 4,000

F

0%

$        0

0%

$        0

a. Use the earned value approach to calculate BCWP, BCWS, ACWP, SV, CV, SI, and CI for each task and the whole project at Week1.

b. Calculate the total variance and time variance for the project at the end of week 2.

c. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 1.

d. Use the original estimate approach and the revised estimate approach to respectively estimate the final cost of this project at the end of week 2.

3. A manufacturer of communication systems currently overhauls its computerized payroll system. Instead of using LOC (lines of code) to track the effort on devel­oping such a payroll system, the manufacturer adopts a more reliable method, function point analysis, for measuring/monitoring the progress of the project.

The new payroll system consists of eight modules, each with a certain amount of function points. From the manufacturer's experience, each function point takes one week to develop. The ongoing project is evaluated at the end of the eighth week after its start.  The schedule/cost report is provided in the follow­ing table. (Assume linearity of cost vs. function point in each module.)

Comment on the status of the project at the end of week 8 based on the calculation of the project BCWP, BCWS, and ACWP. Is the project "in control"?; if not, why not?

Module

Immediate
Predecessors

Function
Points

Budget
(K)

Completed
Function Point

Money Spent
(K)

A

 

4

$90

4

$110

B

A

3

$65

3

$ 35

C

A

6

$75

2

$ 40

D

B

3

$60

3

$ 75

E

C

8

$55

1

$ 20

F

C

2

$40

1

$ 10

G

D, E

5

$80

0

$ 0

H

F

7

$90

0

$ 0

4.   Sandy Point is the project manager of a small project that consists of seven tasks. After careful and extensive planning, Sandy and her project staff agreed on a proposed project schedule that is indicated by the following Gantt chart:

1503_Chart.png

As indicated in their original project plan, Sandy and her staff had estimated the following durations and (total) direct costs for each task:

Task

Duration (weeks)

Planned Value

A

4

$2800

B

7

$2800

C

3

$1150

D

5

$625

E

5

$1350

F

3

$1050

G

3

$270

This morning (beginning of week 6), Sandy received a progress report; as indicated in the Gantt chart, task C could not be started until this week due to the unexpected delay in completing task A. The report also indicates that task B has been completed two weeks earlier than expected. Information from the progress report is summarized in the following table.

Task

Current

Status

Actual

Expenditures

to Date

Percent of

Work

Completed

A

Completed

$2,000

100%

B

Completed

$2,800

100%

C

Just started

$        0

0%

D

In progress

$ 330

55%

E

Not started

$        0

0%

F

Not started

$        0

0%

G

Not started

$        0

0%

a. As of today (beginning of week 6), what is the cost variance of the proj­ect?   What is the schedule variance of the project?

b. Based on information provided to date, what is your assessment of the cur­rent status of the project?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91421860
  • Price:- $70

Priced at Now at $70, Verified Solution

Have any Question?


Related Questions in Project Management

Case study and research project clairicationfinding a case

Case Study and Research Project Clairication Finding a case for the research project does not mean that you are limited to the company identified in the case. Rather it is to identify an issue identified in the case that ...

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As