Gardener Ltd are considering building a new factory in Leicester. Seven tasks must be performed build the new factory and estimates of the duration for each task are shown below along with the precedence relationships for these tasks.

TASK

Optimistic Estimate (days)

Most Likely Estimate (days)

Pessimistic estimate (days)

Immediate predecessors

A

4

8

10

-

B

1

3

4

-

C

3

7

10

A

D

1

7

13

A

E

1

3

5

B,D

F

7

8

10

E

G

6

7

10

C

 Gardener Ltd will receive a subsidy of £500,000 if it is completed in the next 22 days.

(a) Explain why project management is a useful tool for managers

(b) Draw the network diagram for this project and identify the critical path

(c) Find the estimate for mean and variance of the duration of each activity and the mean duration of the critical path

(d) Calculate the probability of completing the project within 22 days, stating any assumptions that you make?

(e) What action could be taken to improve the chances of completion within 22 days?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9743801

Have any Question?


Related Questions in Project Management

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Assessment descriptionyou are required to read a case study

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. Case Study - DeGrand ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Case study and research project clairicationfinding a case

Case Study and Research Project Clairication Finding a case for the research project does not mean that you are limited to the company identified in the case. Rather it is to identify an issue identified in the case that ...

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

Developing an innovative solution to a problem involves

Developing an innovative solution to a problem involves several steps.kindly elaborate?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As