Project has just completed 87th item in its action plan. It was scheduled to have spent $168,000 at this point in plan, but has actually spent only $156,000. Foreman evaluates that value of work actually finished is about $162,000. prepare down the spending and schedule variances for project? Determine the SPI and CPI?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M933292

Have any Question? 


Related Questions in Project Management

Identify one balancing loop and one reinforcing loop these

Identify one Balancing Loop and one Reinforcing Loop. These feedback loops should be critical to Whole Foods Market's performance and success. You should have a good idea of what these are from your previous analysis. Ex ...

Project planthis assignment consists of three sections a

Project Plan This assignment consists of three sections: a written project plan, a revised Gantt chart or project plan, and a project plan PowerPoint presentation. You must submit the three sections as separate files for ...

Read the following scenario and answer the corresponding

Read the following scenario and answer the corresponding questions upon your completion. You recently earned your Project Management Professional (PMP) certification, and you are excited to share the news with your manag ...

What are the differences between a project operations and a

What are the differences between a project, operations, and a program? Please be sure to provide an example and justification for each. Your response should be at least 200 words in length.

Read the given article and provide a technical discussion

Read the given article and provide a technical discussion and critique of the ideas that are presented. You may use the following questions as prompts, but you are expected to explore the issues and concepts more fully. ...

Change management communication and leadershipduring this

Change Management Communication and Leadership During this course, you have developed many of the artifacts utilized by project managers. You have learned that, contrary to common misconceptions, project managers are inv ...

In the project management world all project managers want

In the project management world, all project managers want to be able to claim they were on time and on budget with respect to projects that they have completed. Search the Internet and retrieve a case study of a project ...

For this assignment you will develop a project plan using

For this Assignment, you will develop a project plan, using as your focus a work-related project you are doing now or will be doing in the future. Part 1: Service Level Agreement It is suggested that the project you sele ...

As an hr manager discuss ways you can promote a wellness

AS an HR manager, discuss ways you can promote a wellness program for all employees and encourage them to join? What incentives can you use to encourage participation without making it mandatory to join? What are the ben ...

Final project frameworkin order to fulfill all parts of

Final Project Framework In order to fulfill all parts of this assignment, you must complete and submit the Assignment Worksheet. This assignment is meant to help you get your Final Project started by: • Focusing on your ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate