For this assignment, you are to build upon your completed Microsoft Project schedule for the "Technology Refresh Project" from Topic 2 by adding resources and resolving any resource over-allocations. You will then determine the display project cost information and will also show the updated (if any) critical path.

Open "Topic 3 Project Resources Information" (a Microsoft Excel file). You will notice in column H that resource names have been added. These resources were already included in the Resource Sheet in the Microsoft Project template file that you worked on during Week 2.

Open the Microsoft Project file that you completed during Week 2 and perform the following.

  1. Ensure that the "Type" field contains "Fixed Duration" for all tasks.
  2. For each lowest-level task, enter the resource names from "Topic 3, Project Resources Information" (a Microsoft Excel file) into the Resources Names field in the your Microsoft Project file. Note that you can simply select the resource(s) using the pull-down menu.

You will notice in the "i" column (i.e., the column with white "i" and blue circle) that certain tasks have a red person displayed. That means that the task has resources that are over-allocated (a resource is assigned more than 8 hours per day on one or more days for that task). These resource over-allocations need to be resolved. To resolve these over-allocations, perform the following:

  1. Again, ensure that the "Type" field contains "Fixed Duration" for all tasks. This ensures when you change the assigned hours for the tasks, the task durations and associated dates will not change.
  2. In the VIEW ribbon, check the "Details" box in the "Split View" group.
  3. In the right bottom of the screen (in the gray area), right click and select "Work."
  4. Go to the first task that has the resource over-allocation. Reduce the hours in the "Work" field and/or assign a different applicable resource in order to resolve the resource over-allocation. Be sure to not alter task durations, start, or finish dates. Also, ensure that your project end date does not change.
  5. You may optionally go to the VIEW ribbon, and select "Resource Graph" in the "Other Views" pull-down menu. This will provide a graph that will specifically show what days a resource is over-allocated.
  6. Repeat item (4) for each task that has a resource over-allocation. Your final Microsoft Project schedule should have no tasks with over-allocated resources. Be sure to take notes that summarize the changes you made.

Display the project cost information and critical path:

  1. Remove the split task screen by double-clicking on the split-task border.
  2. Display cost information by left-clicking on the "Add New Column" field. Select the "Cost" field. Note that since a WBS hierarchy exists, you can see cost information for each summary task, along with the total project cost at the top of the schedule.
  3. Display the critical path: Go to the FORMAT ribbon and check the "Critical Tasks" box in the BAR STYLES group. Note that the critical path task bars will turn red. Also, take note that the Total Slack column contains 0 days for the critical path tasks.

Include the responses to the following:

  1. In summary, what steps did you take to resolve the resource over-allocations?
  2. Did your critical path change? If so, how?
  3. What series of tasks represent the highest cost (as indicated by their summary task)?
  4. What is the total project cost?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92298716
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As