A project is composed of 8 tasks. Three-time estimates (in days) for each activity plus precedence needs for each are given in the table below:

Activity Activity Time Estimates
(in days) ImmediatePredecessor
A 2, 3, 4 None
B 3, 4, 11 None
C 1, 2, 3 A, B
D 4, 5, 12 C
E 3, 5, 7 C
F 2, 3, 4 E
G 2, 3, 10 C
H 2, 3, 4 D, G, F
I 2, 3, 10 D, F
J 1, 2, 3 H
K 1, 2, 3 I, J

A. Sketch network for project by using AON method.
B. Find out the critical path(s) and recognize them by a) double lining arrows connecting activities on CP (like ===) AND b) writing letter representing activities on CP in answer-sheet-set.
C. Do complete path analysis and fill table in answer-sheet set
D. prepare down the probability that project will finish within 25 days?
E. Determine the probability that project will take longer than 23 days to finish?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932403

Have any Question? 


Related Questions in Project Management

Discussionagile schedule development gradedas we have seen

DISCUSSION Agile Schedule Development (graded) As we have seen, traditional and Agile schedule developments are quite different. Agile project management was originally developed to do software development. Could a tradi ...

Mr abebe manager of yyy appliances for addisabeba midtown

Mr. Abebe, Manager of YYY appliances for addisabeba midtown department store feels that her inventory levels of stoves have been running higher than necessary. Before revising the inventory policy for stoves she records ...

Write in 450 wordswebliography contributionover the length

Write in 450 WORDS. Webliography Contribution Over the length of the course, upload three separate URL references to articles relating to current healthcare insurance and managed healthcare issues. Explain the relevance ...

Read the given case studyand answer the following

Read the given case study.and answer the following question:- QUESTIONS 1. Why might peer or co-worker evaluations be necessary to evaluate values? 2. Do you think evaluations of values should receive equal, more, or les ...

Think about it culture and its two main aspects-1 the

Think about IT culture and its two main aspects-(1) the structural placement of the IT function within an organization and (2) the philosophical approach to the development, deployment, and use of IT. In terms of changin ...

Investigate satellite radioat the time of writing there

INVESTIGATE SATELLITE RADIO At the time of writing, there were two satellite radio services: Sirius and XM. Do a little surfing on the Web and find out if there are any others now. Also find out what you have to buy to i ...

Consider the differences and similarities among the four ai

Consider the differences and similarities among the four AI techniques discussed in this chapter. Name some problems that might be amenable to more than one type of AI system. Say you sell baseballs from your Web site. W ...

Part 1 service level agreementit is suggested that the

Part 1: Service Level Agreement It is suggested that the project you select be manageable in scope and not overly complex. You will assume that the objectives and scope of the project you have selected have been vetted a ...

1 why can the process of commercialization take a

1. Why can the process of commercialization take a considerable amount of time? 2. What is product differentiation, and how can it be achieved? 3. Explain how the term quality has been used to differentiate products in t ...

A rapid-response maintenance company serves its customers

A rapid-response maintenance company serves its customers who are located in four industrial estates. Estate A has15 customers and is located at grid reference (5,7). Estate B has 20 customers and is located at grid refe ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro