Activity Immediate Predecessor(s) Activity Time (days)
A - 7
B A 2
C A 4
D B, C 4
E D 4
F E 3
G E 5

a. Sketch network diagram for this project.

b. Find out critical path and project duration.

c. Compute slack for each activity.

d. Evaluate probability that noncritical path B-F-G will take more than 20 weeks. Subtract from 1.0 which probability that B-F-G will take more than 20 weeks or less.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932474

Have any Question? 


Related Questions in Project Management

1 describe three buying experiences you have had- one for

1. Describe three buying experiences you have had- one for each type of problem solving-and identify which problem-solving process you used. Discuss why that particular process was appropriate. 2. Interview a classmate a ...

Visit the website wwwcovisintcom and evaluate the nature of

Visit the website www.covisint.com, and evaluate the nature of the business customers attracted. Who is the target audience for this business marketing site? Describe the types of firms that are currently doing business ...

What are the main advantages and disadvantages of

What are the main advantages and disadvantages of multicultural arrangements in engineering, procurement and construction projects?

Discussionas we have seen this week project scope creation

DISCUSSION As we have seen this week, project scope creation is very different in traditional project management versus Agile project management. What advantages and disadvantages can you see with the process of scope cr ...

Pect 1-21 titletechnology management plan2

Project 1-2 1. Title Technology Management Plan 2. Introduction You have been selected to be the acting CIO for a subsidiary of Largo Corporation called Rustic Americana. Its primary products include arts and crafts that ...

He has heard of eoq as a basis for setting the length of

He has heard of EOQ as a basis for setting the length of production runs. What values should he assign to cp and cH for his operations?

1 how does addressability differentiate e-marketing from

1. How does addressability differentiate e-marketing from the traditional marketing environment? How do marketers use cookies to achieve addressability? 2. Define interactivity, and explain its significance. How can mark ...

1 identify at least one technological advancement and one

1. Identify at least one technological advancement and one sociocultural change that have affected you as a consumer. Explain the impact of each on your needs as a customer. 2. Identify an organization in your community ...

Material requirements planningproduct a is an end item and

MATERIAL REQUIREMENTS PLANNING Product A is an end item and is made from two units of B and four units of C. B is made of three units of D and two units of E. C Is made of two units of F and two units of E. A has a lead ...

In october 2010 boeing announced a record charge of 11

In October 2010, Boeing announced a record charge of $11 answer below »In October 2010, Boeing announced a record charge of $1 billion related to delays in delivering its new Dream liner 747 8 jumbo jet. As an investor w ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro