Ask Project Management Expert

Earned Value Management Journal Guidelines

Assignment: On April 8, one week before the first internal project review is scheduled to take place, Spencer Tracey and Margaret Porter are reviewing the presentation that Spencer intends to make to their vice president.  Spencer is the project manager and Margaret is the contract manager. The project they are working on has the potential to generate 10 billion dollars over the next 7 years but only if the first year of the project is successfully completed on time (December 31) and within budget ($110 million).  

At this point in April, the project is reporting out its status on the first 25% of the work. Spencer feels optimistic about the outcome. He plans to report that the project is on track financially and is still tracking to plan. All tasks for January and February were completed on time; however, a few tasks in March began to slip. These tasks were caught early enough to implement a corrective action to ensure they finished on time. During the 2nd and 3rd weeks of March, overtime was added to bring the past due tasks back in line with the schedule baseline.

Based off this analysis, Spencer believes he will finish the project under budget at about $100 million dollars and on time. Margaret congratulates Spencer on his success so far and asks if she can review the numbers more closely. Spencer agrees and provides her with the following data:

Work Unit

Completion Date

$M Budget

Planned Percent Complete

Actual Percent Complete

$M Actual Costs

A

Jan 31

4

100

100

5

B

Feb 28

6

100

100

8

C

Mar 31

10

100

80

12

D

Jun 30

30

0

0

 

E

Aug 31

26

0

0

 

F

Oct 31

20

0

0

 

G

Nov 30

2

0

0

 

H

Dec 31

2

0

0

 

Margaret decides to add another column, which she calls the earned value (EV) analysis.  

Complete Margaret's EV chart and answer the questions above based on the earned value analysis of the project. Fill in the missing data in the empty spaces.

Work Unit

Completion Date

$M Budget

Planned Percent Complete

Actual Percent Complete

$M Actual Costs

EV

A

Jan 31

4

100

100

5

 

B

Feb 28

6

100

100

8

 

C

Mar 31

10

100

80

12

 

To Date

April 8

 

------

-------

 

 

D

Jun 30

30

0

0

-------

-------

E

Aug 31

26

0

0

-------

-------

F

Oct 31

20

0

0

-------

-------

G

Nov 30

2

0

0

-------

-------

H

Dec 31

2

0

0

-------

-------

Complete the following earned value calculations to determine the overall status of the project and projected outcome:  

Cost Variance (CV)

Schedule Variance (SV)

Cost Performance Index (CPI) 

Schedule Performance Index (SPI)

Estimate at Completion (EAC)

Estimate to Complete (ETC)

Variance at Completion (VAC)   

If you were Margaret, what would be your analysis of Spencer's plan, current status, and probable outcome of the project? Is the project on schedule and on budget?

Network Diagram Journal Activity

Now that you have created the work breakdown structure and received approval to begin scheduling the office move, your manager, Steve Spaniels, would like to review a network diagram and present it to the CEO.

You have worked with your project team to estimate the durations of each of the work packages in the WBS. The following is your current plan:

Work Package

Duration (days)

Predecessors

1) Initial planning

20

 

2) Kick-off meeting

1

 

3) Decide on furniture

25

 

4) Office preparation

20

 

5) Actual move

5

 

6) Build out of new facility

45

 

7) Install of furniture/servers/equipment

10

 

8) Set up utilities

30

 

9) Pack-out existing office

10

 

10) Install new company signs

15

 

11) Closeout activities

5

 

Assignment:

Please review the Network Diagraming. Create a project network diagram by first identifying the task predecessors (above).  Once you have completed the network diagram:

1) Calculate the forward pass and backward pass.

2) Calculate activity slack and project float.

3) Identify critical path.

Attachment:- Assignment.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92194986
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As