Earned Value Exercise

Complete the following problems:

1. The following project is at the end of its first week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

2

500

650

100

B

None

3

1000

1500

100

C

A

2

200

300

50

D

A

5

600

600

20

E

B ,C

6

1200

550

10

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

2. Using the following information, calculate the cost performance index and the schedule performance index. Then calculate the estimate at c

Planned value: 6700

Earned value: 6100

Actual costs: 7300

Budget at completion: 38900

CPI _______________________                    SPI  _____________________________

EAC ______________________

3. The following project is at the end of its third week. Find the cost and schedule variances, the cost performance index, the schedule performance index and the estimate at completion.

Task

Predecessors

Duration in days

Planned Value ($)

Actual Cost ($)

Percent Complete

A

None

3

600

650

100

B

A

5

1000

1500

100

C

A

2

200

300

100

D

A

5

1000

600

100

E

B ,C

6

1200

1200

100

F

C

10

10000

12000

75

G

F

7

700

0

0

H

G

8

1600

0

0

To do this exercise, it is best to start with a Gantt chart depicting the task relationships.

CV ______________________     CPI ________________

SV ______________________      SPI ________________

EAC _____________________

4. Mary is the project manager for a web design project for Newberry Pet Foods. So far in the six weeks (of the twelve week project), Mary's team has completed five tasks which had a combined planned value of $7800. However, the team spent $8200 to complete those tasks. She has five additional tasks to complete the project.  What are the PV, EV, AC, CV, SV, CPI, and SPI for Mary's project?

5.  Consider the following information:

PV=6500

EV=5000

AC=7200

BAC=32000

Expected Duration=12 weeks

Calculate the following:

CV __________________

SV __________________

CPI __________________

SPI __________________

EAC __________________

Duration at Completion _______________

Management Information System, Management Studies

  • Category:- Management Information System
  • Reference No.:- M92296564
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Management Information System

Search the csu library the internet or any specific

Search the CSU library, the Internet, or any specific websites, and scan IT industry magazines to find an example of an IT project that had problems due to organizational issues. Write a paper summarizing the key stakeho ...

Question how can company protect the new emerging

Question : How can company protect the new emerging technology ventures from profit pressures of the parent organization (APA format required, Turntin check required . Minimum 250 words essay) How do companies overcome l ...

Communication and team decision makingpart 1 sharpening the

Communication and Team Decision Making Part 1: Sharpening the Team Mind: Communication and Collective Intelligence A. What are some of the possible biases and points of error that may arise in team communication systems? ...

Question provide an explanation of ifwherehow does active

Question : Provide an explanation of if/where/how does Active Directory support network security,14 pages (2,000-2,500) in APA format. Include abstract and conclusion. Do not include wikis, message boards, support forums ...

Question how companies could effectively use emerging

Question : How companies could effectively use emerging technology to win over its competitors. APA format required. 250 words essay required. The response must be typed, single spaced, must be in times new roman font (s ...

Question how customers could effectively use emerging

Question : How customers could effectively use emerging technology to win over its customers. APA format required. 250 words essay required. turntin check require. The response must be typed, single spaced, must be in ti ...

Part 1 - create an 8 slide powerpoint presentation on

Part 1 - Create an 8 slide PowerPoint presentation on foundational concepts specific to physical security. Part 2 - Write 4 pages detailing the framework for the design of an integrated data center. Assessment Instructio ...

In chapter 2 of the text - managing amp using information

In Chapter 2 of the text - Managing & Using Information Systems: A Strategic Approach, the chapter discusses why information systems experience failure often because of organizational strategy. A classic example of this ...

Review at least 4 articles on balanced scorecard and

Review at least 4 articles on Balanced Scorecard and complete the following activities: 1. Write annotated summary of each article. Use APA throughout. 2. As an IT professional, discuss how you will use Balanced Scorecar ...

Data resources management questionsq1 the dama dmbok

Data Resources Management QUESTIONS Q1. The DAMA DMBOK textbook describes the following two core activities as part of the Data Architecture management exercise: "Understanding enterprise information needs" and "Develop ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As