Download the spreadsheet, gantt-chart_L.xls, from the Files area of this course.

Open the spreadsheet and read the terms of use (on the 2nd worksheet tab)

Use the data from the following table to populate the Gantt chart. You can either treat these as individual tasks, or just make these subtasks of a single task. Either way, you'll need to read the instructions in the spreadsheet to add some rows.

Description

Task

Must follow

Expected Time (Days)

Meetings for ideas

P

None

9

Information Searching for the game

Q

P

12

Draft design of the gameplay

R

Q

3

Write up the story lines

S

R, Z

7

Write up the specification of the game

T

P

11

Draft the proposal

X

None

8

Finalize the proposal with members

Y

X

14

Design the main characters

Z

T, Y

5


(This particular set of tasks is from Jamson Chan, formerly available at http://mh-ict.vtc.edu.hk/~mtchan/cgd/ganttChartExercise2.doc)

Leave the start date for the entire project as September 7, 2015. You may set the amount completed to any reasonable value, or just leave it at 0. Put your name in the spreadsheet replacing the field Project Lead. You should only change data fields, not formulas. The data fields are all colored light green. If you think you need to change some other color field, talk to the instructor first.

In a separate document, write a paragraph or two about why you think your Gantt chart is correct. What do you like about this way of creating a Gantt chart? What do you dislike? What are some limitations that you see with this approach? What should happen when you change the length of time for Task P, Meetings for ideas, from 9 to 15 days? What actually happens?

For extra credit, read the Help section (gray colored area on the spreadsheet) and fix the spreadsheet so that it can automatically adjust dates based on the lengths of prior tasks. If you complete this, add a brief description of your changes to your report. This is worth up to an additional 2 points on this assignment.

Attachment:- gantt-chart_l_0.xls

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91409566
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Project Management

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Assessment descriptionyou are required to read a case

Assessment Description You are required to read a case study based on a fictional company and prepare a Performance Evaluation Video Presentation based on the information contained in the case study. The case study will ...

Define quality management philosophy and identify which

Define quality management philosophy and identify which quality guru worked with Toyota to make it a success?

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

How can you assist in determining human resource

How can you assist in determining human resource requirements and How can you contribute to establishing and maintaining productive team relationships?

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As