It is critical to develop a time-phased baseline to make sure the project is on track. Just looking at the project, it is easy to assume results, costs or needs but it should always be based on actuality not assumptions. With a time-phased baseline the project can be examined and the project manager can accurately determine where the project is in relativity to the schedule, is it behind, on time or ahead of schedule. It also helps determine where the budget is, is it over budget, under budget and why.

Once you have the baseline and are in the middle of the project it is important to look at the progress and decide if leveling is needed so non-critical activities can be delayed to push critical activities ahead. Using leveling creates a risk of losing flexibility and of also creating more critical activities because the slack has been reduced. In our project at work, we have leveled out some of the activities because they were deemed non-critical. The non-critical activity that we delayed was changing up one of our systems because it was deemed not necessary to accomplish the scope of the project, however it created technical issues that were unforeseen. By not changing the program in the way that we wanted to it made a ripple in the way work flows through the system. Now we are putting out fires with the system because not only is the project crashing, the current system that we are working in is crashing as well. Something that was thought to be unnecessary turned out to be critically important and has jeopardized the project.

That is the risk that we are taking because the project has time constraints imposed on it and because of that decisions are being made to ensure the project meets those deadlines knowing that there are going to be issues popping up that are considered acceptable as long as the work keeps flowing.

Discussion 2

Resource leveling is defined as, "a technique in which start and finish dates are adjusted based on resource constraints with the goal of balancing demand for resources with the available supply", (Project Management). With every technique, there are always associated risks. As an example, my company is currently undergoing a project to engineer a new flow meter. This project involves the dedication and focus for the next year from our design engineers. At the same time, our customers are experiencing problems with flow meter x in the field. To help with the customers out in the field, flow meter x has been sent back to the facility for further evaluation. As the company tries utilizing the design engineers for the new flow meter and help evaluate flow meter x, they end up delaying a non-critical part of the new design project. The risk here is the company has now increased the demand of the design engineers and strayed them away from the initial project plan.

Crashing projects is defined as, "a technique used to shorten the schedule duration for the least incremental cost by adding resources", (Project Management). At my company, we experience crashing projects on a monthly basis. For background knowledge, my company makes custom built flow meters. Some when order can take two weeks and others fourteen weeks. Most of the time a contractor will call us because they've forgotten to order the flow meter for their project that is installing about one week from today. The meter they order has a typical lead time of four to six weeks. Due to the contractor "dropping the ball" on the flow meter, they ask to expedite the meter. This expedite is possible however the risk for the contractor then becomes, a major increase on the cost of the meter and if the meter will make it on site at the exact time installation is occurring.

Developing a schedule is defined as, "the process of analyzing activity sequences, durations, resource requirements, and schedule constraints to create the project schedule model", (Project Management). It is critical to develop a time-phased baseline because this will help plan the project schedule as well as the cost of the project. The time-phased baseline allows a project manager to see if items are on track and if they are not. Without this feature the project manager has nothing to base their accomplishments on or if they are within the project budget.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92355779
  • Price:- $20

Priced at Now at $20, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As