Scenario: You are a consultant with expertise in project management strategies. Select a possible project management situation from your current or future professional experience. As a project management consultant, you are tasked with developing a project management plan for this project. Your goal is to maximize the time, resources and finances associated with the project in the best interests of the business/company. You will need to write a professional memo to the business/company owner describing the management of the project.

Use Excel QM to create the project. See video in Live Binder. Your professional memo should include:

1. Create the PERT/CPM activity network for your project that includes at least five activities and at least one predecessor activity.
2. Estimate the optimistic, most likely, and pessimistic times to then determine an expected time for each activity.
3. Determine all activities that are on the critical path.
4. Identify the slack time (if any) associated with activities in the project.
5. Create a Gantt chart to show the project timeline.

Address the following questions in your professional memo:

• What is the overall timeline for this project?
• What activities are critical for established timeline of the project?
• What activities have flexibility in completion that would not impact the overall project timeline?
• What time, resources and money might be affected by any changes to activities throughout the project?
• What recommendations would you suggest to prioritize the company's time, resources and money with regards to the project?

1 & 2) I am a project management expert tasked with managing a project in my current or future profession. I will suggest a course revision for a class. The time estimates are in weeks.

Tasks

optimistic

average

pessimistic

Predecessor

A - Select new textbook

4

6

10

 

B - Create unit assignments

5

8

12

A

C - Select topics for units

1

2

3

A

D - Set up gradebook

1

2

3

B

E - Review content

2

4

6

B

3) Activities on the critical path? All activities with slack time = 0 are on the critical path: A - Select new textbook, B - Create unit assignments, E - Review content

4) Slack time:

Results

 

 

 

 

 

Activity

Early Start

Early Finish

Late Start

Late Finish

Slack

A

0

6.333333

0

6.333333

0

B

6.333333

14.5

6.333333

14.5

0

C

6.333333

8.333333

16.5

18.5

10.16667

D

14.5

16.5

16.5

18.5

2

E

14.5

18.5

14.5

18.5

0

 

Project

18.5

 

 

 

5) Gantt Chart showing Early Start Times:

Now, using the above computations and write your discussion response as a professional memo.

1740_Gantt Chart.jpg

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92372968
  • Price:- $45

Priced at Now at $45, Verified Solution

Have any Question?


Related Questions in Project Management

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Case study and research project clairicationfinding a case

Case Study and Research Project Clairication Finding a case for the research project does not mean that you are limited to the company identified in the case. Rather it is to identify an issue identified in the case that ...

Developing an innovative solution to a problem involves

Developing an innovative solution to a problem involves several steps.kindly elaborate?

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

How can you assist in determining human resource

How can you assist in determining human resource requirements and How can you contribute to establishing and maintaining productive team relationships?

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As