Q1) Discuss the pros and cons of the checklist versus the weighted factor method of selecting projects.
Q2) On day 51 a project has an earned value of $600, an actual cost of $650, and a planned cost of $560. Compute the SV, CV, and CPI for the project. What is your assessment of the project on day 51?