You are working on the project which has 12 activities. You find out that critical path comprises of only five activities. You then find out the variances for five critical path activities and these variances are 3, 4, 2, 1, and 6 days. Desired completion date for project is 44 days and expected completion date for project is 40 days. Which of the given alternatives gives the probability that project will be completed by desired completion date?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M931945

Have any Question? 


Related Questions in Project Management

It project management techniques assignmenttask - team

IT Project Management Techniques Assignment Task - Team Project Management Plan. Objectives - This assessment task relates to the following course objectives: Identify traditional and agile approaches and lifecycles for ...

Explain how project management has evolved from 1945 to the

Explain how project management has evolved from 1945 to the present day. Provide one example of a major change in project management that occurred during this time period, and explain its significance. Your response shou ...

Project management- international project and project

Project Management- : International Project and Project Oversight The Project Management Maturity Model (PM3) is a model that allows us to describe our organization's functioning level related to Project Management pract ...

As an hr manager discuss ways you can promote a wellness

AS an HR manager, discuss ways you can promote a wellness program for all employees and encourage them to join? What incentives can you use to encourage participation without making it mandatory to join? What are the ben ...

Cases and examplesastro bankthe management of the project

Cases and examples Astro Bank The management of the project teams for both the legacy and new systems started badly. Separate project teams were established for each. No roles, responsibilities, or rules were established ...

Your ceo is a visionary who wants you to transform the way

Your CEO is a visionary who wants you to transform the way the company conducts business. She is fascinated by computer software for project management and requires that you conduct a SWOT analysis of this service in rel ...

Fundamentals of project managementdefining the projectusing

Fundamentals of Project Management Defining the Project Using the South University Online Library or the Internet, research, select, and scope out any project of your choice. The project you select must meet the followin ...

Project management life cycle modeldevelop a report

Project Management Life Cycle Model Develop a report utilizing the Project Management Life Cycle (PMLC) model ((initiation, planning, execution, and closure), and reporting it to your client. Also, prepare a summary anal ...

1 create a network diagram aon2 identify the paths through

1. Create a network diagram (AON) 2 Identify the paths through the network diagram 3 State the critical path and the project duration Attachment:- template.rar

Operations managementdiscussionprocess selection product

Operations Management Discussion Process Selection: Product Design and Capacity How is process selection related to product design and capacity determination? Your initial post should be 200-250 words. Discussion 2 Moniq ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate