You are working on the project which has 12 activities. You find out that critical path comprises of only five activities. You then find out the variances for five critical path activities and these variances are 3, 4, 2, 1, and 6 days. Desired completion date for project is 44 days and expected completion date for project is 40 days. Which of the given alternatives gives the probability that project will be completed by desired completion date?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M931945

Have any Question? 


Related Questions in Project Management

Discussion1 thinking back what lessons learned from our

DISCUSSION 1) Thinking back. What Lessons Learned from our CBMC Communications Project had thegreatest impact for you personally? What recommendations (at least 2) would you give to make such a project run smoother? 2) T ...

Create a powerpoint presentation to support your plan plan

Create a PowerPoint presentation to support your plan (Plan is attached). Submit 25 - 30 PowerPoint slides with complete speaker's notes presenting your project comprising of all the sections and references. The project ...

1creating opportunities discussionexplore the value of

1.CREATING OPPORTUNITIES DISCUSSION Explore the value of regarding problems as opportunities for teams. Instructions Teams must be equipped to address problems as they arise. If handled effectively, problems can become o ...

Assessmentnote the assessments in this course build upon

Assessment Note: The assessments in this course build upon each other, so you are strongly encouraged to complete them in sequence. For this assessment, describe a project you have been a part of, which underwent some so ...

Questionyou are an employee of grand wines ltd and project

Question: You are an employee of Grand Wines Ltd and project leader of a proposed project to equip each of the company's 20 sales representatives with a wireless data entry device by which they could instantly communicat ...

Assignmentlength 2 pagesproject choices1 kitchen

Assignment Length: 2 Pages Project Choices: 1. Kitchen Remodel (commercial) remodel a kitchen that is used for chefs competing in some televised broadcasts. The idea of the project preparation and renewal of a kitchen fu ...

Erp for the small business most major erp vendors have been

ERP FOR THE SMALL BUSINESS Most major ERP vendors have been focusing on selling multimillion dollar installations of their software to very large organizations. That is shifting in focus somewhat as ERP vendors realize t ...

Part a project schedule1in assignment you developed a

Part A: Project Schedule 1. In Assignment, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule. Your proj ...

Analyse all the activities mapped and assessevaluate all

Analyse all the activities mapped and assess/evaluate all these activities in order to specify and characterize their strengths and weaknesses (namely when compared to one major competitor that you should choose). Additi ...

This assignment consists of two parts a project schedule

This assignment consists of two parts: a project schedule, and a written response. You must submit both parts as separate files for the completion of this assignment. Label each file name according to the part of the ass ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro