Davis v. Baugh Industrial Contractors, Inc.
Supreme Court of Washington
159 Wash.2d 413, 150 P.3d 545 (2007)

Case Background Glacier Northwest hired Baugh Industrial Contactors to build a processing facility that included a system of underground pipes. Three years later, Glacier suspected a leak in a pipe. It assigned an employee, Alan Davis, to uncover the leak, which he did. While he was down in a hole dug to get to the pipes, a concrete wall collapsed, killing him. While the pipes were supposed to last 100 years, it is likely they had been damaged when installed, resulting in a leak. Tami Davis, Alan's daughter, sued Baugh and others, contending their negligent practices were the cause of Alan's death.

The trial court, called the superior court, held for Baugh and dismissed the suit. Under the traditional common law rule, the contractor was not liable for such an accident, so the risk of liability was on the property owner, Glacier. This decision was appealed to the Washington state high court which then issued this decision.

Case Decision Chambers, Justice

Under the completion and acceptance doctrine, once an independent contractor finishes work on a project, and the work has been accepted by the owner, the contractor is no longer liable for injuries to third parties, even if the work was negligently performed. Historically, after completion and acceptance, the risk of liability for the project belonged solely to the property owner. This court has not addressed this doctrine in over 40 yeajrs and, in the meantime, 37 states have rejected it. Under the modern...approach, a builder or construction contractor is liable for injury or damage to a third person as a result of negligent work, even after completion and acceptance of that work, when it was reasonably foreseeable that a third person would be injured due to that negligence.

We join the vast majority of our sister states and abandon the ancient Completion and Acceptance Doctrine. We find it does not accord with currently accepted principles of liability...

The Completion and Acceptance Doctrine is also grounded in the assumption that if owners of land inspect and accept the work, the owner should be responsible for any defects in that accepted work. While this assumption may have been well founded in the mists of history, it can no longer be justified. Today, wood and metal have been replaced with laminates, composites, and aggregates. Glue has been replaced with molecularly altered adhesives. Wiring, plumbing, and other mechanical components are increasingly concealed in conduits or buried under the earth. In short, construction has become highly scientific and complex. Landowners increasingly hire contractors for their expertise and a non-expert landowner is often incapable of recognizing substandard performance....

We conclude that the Doctrine of Completion and Acceptance is outmoded, incorrect, and harmful and join the modern majority of states that have abandoned it in favor of the [modern] approach [holding a builder or contractor liable for injury due to negligent work]. We reverse the superior court order...and remand for further proceedings in keeping with this holding.

Questions for Analysis
1. The court rejected the common law rule concerning completion and acceptance that had been in effect until this decision and ordered a new trial. What was the key reason for that decision? How does the new rule affect liability?

2. A judge on the court dissented from the decision. Explaining his opposition to the decision of the majority, he said this change in the law should have been done by the legislature in a statute, not the court. What are the practical problems with such a view?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91945650

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As