Information given in the following table

Activity Duration Predecessor
a 4 None
b 6 a
c 4 a
d 2 c
e 4 b
f 5 b, d
g 3 c
h 4 f,g
i 2 e, h

a. Create the network diagram
b. Recognize each activity's EST, EFT, LST adn LFT
c. Recognize all paths. Which path is the critical path?
d. Compute slack each activity?
e. How long will it take to complete project?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932492

Have any Question? 


Related Questions in Project Management

In the exercise extend situation calculus to allow for

In the exercise, extend situation calculus to allow for actions that take place simultaneously. Use a function called Simultaneously, which takes two actions as arguments and denotes the combined action. Consider a grid ...

1 leadership value discussionexplain the importance of a

1. LEADERSHIP VALUE DISCUSSION Explain the importance of a team leader. Instructions A team leader must organize the members and distribute the necessary tasks. Team leaders are responsible for supervising the team and a ...

International truck makes a huge bet on a service -

INTERNATIONAL TRUCK MAKES A HUGE BET ON A SERVICE - ORIENTED ARCHITECTURE Service-oriented architectures (SoAs) do seem to be the future for integrated IT systems within an organization, bringing together both applicatio ...

Investigate building your own home networkbuild your own

INVESTIGATE BUILDING YOUR OWN HOME NETWORK Build your own home network on paper. Assume you have the computers already and just need to link them together. Find prices for switches and routers on the Web. Also research E ...

It is said that if you are not leading change you are not

It is said that if you are not leading change, you are not leading. Relate given statement to planned and unplanned change as well as to one or more approaches to change previously presented in this course. Do you agree ...

People often think that a system is complete once it is

People often think that a system is complete once it is implemented. Is this true? What happens after a system is implemented? What can you do to ensure the system continues to meet the knowledge workers' needs?

Project management and erppart 1 answer the module review

Project Management and ERP Part 1: Answer the module review questions listed below. 1. What is the role of a project manager and program manager? What are the skills, knowledge, and abilities required to be a project man ...

Pretest your questionnaire by giving it to tree peopleask

Pretest your questionnaire by giving it to tree people. Ask for their reactions to each question, looking for potential problems in how the questions are worded and in the response formats that you used.

Discussionmiddot assess the value of the product

Discussion · Assess the value of the product life cycle as a tool for product succession planning and related product management activities. Give your opinion on whether or not the Product Life Cycle can help health care ...

Project assignmenta project is a set of definable tasks

Project Assignment A project is a set of definable tasks related to each other. The project has a beginning and end and a budget of money and resources. It should have a clear objective. For the project assignment you wi ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro