Compute true status of the project on tasks a and b. Information that is given is:

Budgeted Work/Cost (PV)
Actual Cost to date (AC)
% work completed
Estimate to complete
Planned start & end dates - Start is Jan. 1, End is April 30
Actual start date - Feb. 1
Projected end date
Planned Resources Utilized - 30%
Actual Resources Utilized - 45%

With Cost one computes PV EV and AC.

The formula concerning schedule and cost refers to financial data but when there are only dates how does that calculation go?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M931953

Have any Question? 


Related Questions in Project Management

Project deliverable project planthis assignment consists of

Project Deliverable: Project Plan This assignment consists of three sections: a written project plan, revised business requirements document, project plan PowerPoint presentation, and a finalized project plan. You must s ...

Change management communication and leadershipduring this

Change Management Communication and Leadership During this course, you have developed many of the artifacts utilized by project managers. You have learned that, contrary to common misconceptions, project managers are inv ...

Assignment lasa - final project reportprepare an 8-10-page

Assignment: LASA - Final Project Report Prepare an 8-10-page report in Word. This report should include a project history of your recent Trillo Apparel Company District 4 Production Warehouse Move experience over the las ...

Taskpart oneproject name team descriptionworking as a

Task Part One: Project Name / Team / Description Working as a team you are to - Agree on a suitable team name, list all team members and provide their contact details in a professional looking document. - Provide an over ...

Project descriptiona team is solving the problem of time

Project Description A team is solving the problem of time and attention required to maintain environmental control of an Aquaponics system.Various aspects of an Aquaponics system need monitored and adjusted to maintain a ...

Assessment 1 - project workpart aoverviewyou are required

ASSESSMENT 1 - PROJECT WORK Part A Overview You are required to develop a project management plans, for given scenarios. These project plans requires you to: - Implement start-up activities through updating and confirmin ...

Case studyread the following scenario and answer the

Case Study Read the following scenario and answer the corresponding questions upon your completion. You recently earned your Project Management Professional (PMP) certification, and you are excited to share the news with ...

Project management life cycle modeldevelop a report

Project Management Life Cycle Model Develop a report utilizing the Project Management Life Cycle (PMLC) model ((initiation, planning, execution, and closure), and reporting it to your client. Also, prepare a summary anal ...

Project management- international project and project

Project Management- : International Project and Project Oversight The Project Management Maturity Model (PM3) is a model that allows us to describe our organization's functioning level related to Project Management pract ...

Carlton speciality plc is a small family owned firm that

Carlton Speciality PLC is a small family owned firm that manufactures custom made furniture and uses job costing system. The company does not have computerised system and thus maintains all accounting records on hard cop ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate