Company X has been told to install new equipment. Company has 16 weeks to install equipment. Using following information:

IMMEDIATE ACTIVITY TIMES
ACTIVITY PREDECESSORS a m b

A --- 1 2 3
B --- 2 3 4
C A 1 2 3
D B 2 4 6
E C 1 4 7
F C 1 2 9
G D, E 3 4 11
H F, G 1 2 3

1.) Determine the Critical Path?

2.) Compute the expected completion time?

3.) Which activities have slack time and what are their respected slack times?

4.) Determine the probability that project can be finished in 16 weeks?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932495

Have any Question? 


Related Questions in Project Management

Questionsome of the key issues in supply chain management

Question: Some of the key issues in supply chain management are obstacles to process integration along the supply chain. Using Table 13.2 in Chapter 13, identify one obstacle that you have encountered in your experience, ...

Operations managementdiscussionprocess selection product

Operations Management Discussion Process Selection: Product Design and Capacity How is process selection related to product design and capacity determination? Your initial post should be 200-250 words. Discussion 2 Moniq ...

Assignment discussion questionimportant note discussion

Assignment: Discussion Question Important note: Discussion questions in this course use a case study that is found in Doc Sharing area in the file named "Project Management Case.docx." It is strongly recommended that you ...

Your ceo is a visionary who wants you to transform the way

Your CEO is a visionary who wants you to transform the way the company conducts business. She is fascinated by computer software for project management and requires that you conduct a SWOT analysis of this service in rel ...

Theeggbot project according to the youtube video from the

TheEggBot project, according to the YouTube video from the reference, it is slow and shaky. We assume it was poorly designed so it ended up with shakiness. In addition, we think the slowness is a result of the programing ...

Strategy management course- structure of the project report

Strategy Management course- Structure of the project report (for any international company) 1- Introduction of the company and mission, vision and corporate objectives (1 page) 2- SWOT Analysis: (strengths, weaknesses, o ...

During this discussion talk about and examine the processes

During this discussion, talk about and examine the process(es) of collecting information security measures, how often do they need to be collected, what are the downsides of collecting and reporting the measures too freq ...

Project management planning-because many aspects of health

Project Management Planning- Because many aspects of health care operations are changing, health care administrators oversee a wide variety of projects. These can include logistical projects such as moving a department t ...

Task - weightingyour team should consider a newactual

TASK - WEIGHTING Your team should consider a new(actual/ hypothetical) project. You have to develop a project management plan for the project selected by your group. Your project management plan report shall cover manage ...

Project descriptiona team is solving the problem of time

Project Description A team is solving the problem of time and attention required to maintain environmental control of an Aquaponics system.Various aspects of an Aquaponics system need monitored and adjusted to maintain a ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

A cola-dispensing machine is set to dispense 9 ounces of

A cola-dispensing machine is set to dispense 9 ounces of cola per cup, with a standard deviation of 1.0 ounce. The manuf

What is marketingbullwhat is marketing think back to your

What is Marketing? • "What is marketing"? Think back to your impressions before you started this class versus how you

Question -your client david smith runs a small it

QUESTION - Your client, David Smith runs a small IT consulting business specialising in computer software and techno

Inspection of a random sample of 22 aircraft showed that 15

Inspection of a random sample of 22 aircraft showed that 15 needed repairs to fix a wiring problem that might compromise

Effective hrmquestionhow can an effective hrm system help

Effective HRM Question How can an effective HRM system help facilitate the achievement of an organization's strate