Case Study details -

Organisation Background

Your organisation is a large multinational oil company with multiple storage facilities located around Australia. They own and operate their tank farms in each state to supply the domestic market with automotive fuels. The Project Management Office (PMO) based in Melbourne determines which projects take priority, the scope, and goals for each project along with the terms and conditions for engaging contractors to complete the works.

The Revenue Division of the company has developed a business case for substantial repair works to be completed to reduce environmental fines and optimise availability and throughput of all locations. Throughput equals profit!

Your role: You are the Project Manager, employed to plan and manage a project to bring the Western Australian storage facility up to the required standard, while normal operations continue.

You report to the clients Program Manager in the Project Management Office (PMO) in Melbourne

Situation - Currently 30% of the company's unleaded petrol (ULP) storage capacity in Western Australia (WA) is bordering on collapse due to the age and condition of the tanks and associated infrastructure. The condition of the largest tank in WA is particularly bad due to the tank being over 50 years old and of a complex and outdated design. The company is currently paying $20,000/month in environmental fines due to detected leakage of petroleum products into the surrounding soil.

You are the third Project Manager to be appointed to this project due to performance and personal issues affecting prior appointments. The Health, Safety and Environment (HSE) Manager has worked with you before, but your relationship is tarnished from a disagreement with your in-house HSE Manager.

The Terminal Manager has taken over responsibility for operations in the last 4 months after a promotion and is still working through the logistical challenges of the site. Operations must continue to provide revenue streams and continuity of supply to fuel outlets.

Fuel deliveries for the tanks under repair have been rescheduled to coincide with the planned completion of works as per the schedule.

Required works for the Western Australian site

Tank 1

Capacity: 1 million litres unleaded petrol (ULP)

4 Steel Patches averaging 2m2 in size.

4 Steel anchors required on top of tank for working at heights

Cleaning and repaint of outside of tank

Tank 2

Capacity: 3 million litres unleaded petrol (ULP)

7 Steel Patches averaging 3m2 in size.

4 Steel anchors required on top of tank for working at heights

Cleaning and repaint of outside of tank

Tank 3

Capacity: 7 million litres unleaded petrol (ULP)

6 Steel Patches averaging 1.5m2 in size.

4 Steel anchors required on top of tank for working at heights

Replacement of main supply valve. Size: 300mm Diameter, in Stainless Steel.

Cleaning and repaint of outside of tank

Site challenges

The site is a tapered triangular shape. The longest side is bounded by the loading docks. Another side has a dead-end road leading to the container terminal.

The final side is bounded by a small specialist oil distribution company. The site is on a rise with loading gantry site below the tanks. In order to work on the tanks you will need to use one large crane, one small crane and scaffolding.

When a tanker docks to deliver fuel, all works stops due to highly flammable vapours venting from tanks as they fill.

Time to fill each tank;

Tank 1: 4 to 6 hours

Tank 2: 8 to 10 hours

Tank 3: 18 to 20 hours

Site plan view showing restricted access and internal restrictions created by pipelines.

Assessment details and instructions -

Assessment - Project budget, schedule and resources

Building on Assessment 1, you are a project manager on a major project, and are now required to prepare the relevant documentation for the project budget, schedule and resources. Base your responses on current recommended practice, as described in contemporary literature and personal research into the industry of the Case Study. The focus is to be on the selection and application of appropriate theory, tools and techniques not how accurate your budget, schedule and resourcing are.

Read your project case study carefully. As you work through these three tasks, identify any areas where you do not yet have sufficient information, and may need to ask further questions from your project sponsor.

1. Develop an appropriate budget for the Case Study project. Include details of all assumptions you have made in preparing this budget. (Approximately 400 words)

2. Prepare a schedule for the Case Study project, identifying the key milestones for the project deliverables. Discuss the relative merits of the methods, tools and techniques used and compare these with any that you chose not to use. (Approximately 700 words)

3. Finally, estimate the resources required for successful completion of the Case Study project. Integrate this with the schedule and identify potential resourcing stress points for the "critical path" that will need careful management. Identify tools and techniques that might be used here. (Approximately 700 words)

A report format is acceptable, but must include explanation of the approaches used throughout the project life-cycle. Diagrams, charts, tables and illustrations may be used to communicate or describe an approach. These should be supported by a written discussion and not relied upon to tell the story themselves.

Assessment will be based on your discussion of tools and techniques considered and used to develop and manage the budget, the schedule and to estimate resources. You should discuss the strengths and weaknesses of each approach considered and support your chosen approach to each component for the case.

Attachment:- Assignment File.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92810774

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As