Case Background:

Coastline Systems Consulting is a small solutions provider company located in Destin, Florida. The staff of seven IT technicians, designers, systems analysts, and programmers provides a range of networking, computer hardware, and software solutions to area businesses. Coastline works with clients to analyze their business needs. They then provide a packaged solution that often combines custom-built hardware, purchased software, and custom programming. In addition to the seven technicians, Coastline has one receptionist/bookkeeper.

As a small organization, Coastline is an informal, "shirt-sleeve" environment. Everyone is on a first-name basis, even with Peter Charles, the president.

Task -1: Scope Management Plan

Requirements: List of functions and features in your application

In scope-out scope items: In scope items are list of requirements that are going to be implemented as part of this system. Out scope items are list of functions and features that are not going to be implemented in this project but can be done later for this application.

Deliverables:

Scope verification process: this is built from the Acceptance criteria listed

Task-2: Change Request Form

Use the form in the slides as a reference point and you can add items relevant to your work. Please include items such as what level of changes can be made without further approval, what changes you as a project manager can make, and what changes your sponsor needs to approve.

Task 3: WBS (level 2/3) - Word doc or MS Project

You need to create level 3 WBS. It should have a minimum of 40 tasks. Use the indented format and level 1 as 4 phases of project life cycle.

Task 4: Gantt chart - Firstly you need to do Activity Estimation i.e. estimate the duration of each activity and Secondly dependencies between eh activities need to be determined before you can create a schedule and MS Project builds the Gann chart. You also need to allocate resources to each activity ( 1 resource per activity) from the table given below (PS: You do not need to use all the resources listed below, you may use the ones you need to complete your project)Gantt chart should include all the resources allocated in this project. You should attach the MS project screen shots to prove your workings.

The Resource table to be used for allocating resources is as below

 

 

 

 

$ per Hour

Project Manager

 

 

 

80

Systems Analysis

 

 

 

60

Graphic Designer

 

 

 

50

Application Programmer

 

 

 

50

Web System Expert

 

 

 

70

Program Team member_1

 

 

 

50

Program Team Member_2

 

 

 

50

Quality Assurance Tester

 

 

 

60

Database Administrator

 

 

 

50

Team Member_1

 

 

 

35

Team Member_2

 

 

 

35

 

 

 

 

 

 

 

 

 

 

Total Duration for the Project

 

 

 

6 months

Working Days

 

 

 

5 days per week ( No Over time required)

Working Hours

 

 

 

8 hours per day ( 8.30 - 5.30pm) - 1 hour for lunch

Project Start Date

 

 

 

4 Jan 2016

Task 5: RACI Chart

WBS ACTIVITY Executive Director Directors Project Leader Project Team
1 Develop Leadership Program >< >< >< ><
1.1 Project Development >< >< >< ><
1.1.1 Identify project leader A R I
1.1.2 Identify project team A R C I
1.1.3 Identify goals of program A C R C
1.1.4 Create policy and procedures A C R
1.1.5 Determine format for training
C R
12 Leadership Skills >< >< >< ><
1.2.1 Brainstorm skills to be covered C C R C
1.2.2 Rank skills in order of importance A C R C
1.2.3 Finalize skills to be covered A C R I
1.2.4 Determine class objectives A C R I
1.3 Positions in Needing Training >< >< >< ><
1.3.1 Interview top management C C R
1.3.2 Evaluate organization chart C C R
1.3.3 Select staff positions for focus C C R I

RACI Key: (R Responsible, (A) Approve, (C) Consult, (I) Inform

Task 6: Histogram of demands on each key participant's time from MS Project

Please extract the resource histogram from MS Project and comment on over allocation of resources and sugest how you can level the resource overload if any. If you do not have resource overload please comment why.

Task 7: Create a time-phased budget for your example project using bottom-up estimating. As you allocate resources to the activity your budget is being created. After you extract the Gantt chart, revisit the activity list and be sure to check direct labourcosts for you and your team has been added and add 20% for fringe.

In this section, State all assumptions andconstraints you have used when creating your budget. Give examples of known knowns andknown unknowns( these are financial risks) on your project. Describe how you have budgeted for both of them plus howyou have budgeted for unknown unknowns

Task 8: Risk Register

Create a risk register In the form of a risk register as per the format and example below for your example project.

No.  RANK  RISK  DESCRIPTION  CATEGORY  ROOT CAUSE  TRIGGERS  POTENTIAL RESPONSES  RISK OWNER PROBABILITY  IMPACT  STATUS
R44 1









R21 2









R7 3









For example, the following data might be entered for the first risk in the reg¬ister as follows. Notice that Cliff's team is taking a very proactive approach in managing this risk.

- No.: R44
- Rank: 1
- Risk: New customer
- Description: We have never done a project for this organization before and don't know too much about them. One of our company's strengths is building good customer relationships, which often leads to further proj¬ects with that customer. We might have trouble working with this cus¬tomer since they are new to us.
- Category: People risk
- Root cause: We won a contract to work on a project without really getting to know the customer.
- Diggers: The project manager and other senior managers realize that we don't know much about this customer and could easily misunderstand their needs or expectations.
- Risk Responses: Make sure the project manager is sensitive to the fact that this is a new customer and takes the time to understand them. Have the PM set up a meeting to get to know the customer and clarify their expec-tations. Have Cliff attend the meeting, too.
- Risk owner. Our project manager
- Probability: Medium
- Impact High
- Status: PM will set up the meeting within the week.

After identifying risks, the next step is to understand which risks are most important by performing qualitative risk analysis.

Attachment:- Coast line system.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91619365
  • Price:- $150

Guranteed 48 Hours Delivery, In Price:- $150

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As