As the project manager you are required to present an initial project report to the project sponsor that shows how you propose to implement this project. As the project manager you may make any assumptions you think are necessary.

Case study - Social Media Research Centre

During a meeting with his boss (David Wright), Bruce has been asked to establish a researcher centre. The research centre, which will commence operations in February 2018 first as an informal research group, should be established by June 2017. Alex's decision to proceed with this major project is spurred by the fact that an associated organizational centre, which researches in a closely related area, has recently ceased operations. There is also a tremendous pressure from David's senior executives to produce high quality research that is focused in nature. In fact one of David's senior executives' comments was that David's Unit does not have a clear identity when it comes to its scholarly research output compared to the one in Australian National University. After several meetings with subject matter experts (consultants) and a rigorous analysis of the current trends in research in the area of information technology it has been decided that the most appropriate research area for the proposed research centre to focus on is social media. Fortunately several of David's Unit staff are active researchers in this area. What made this direction even more attractive is that demand from Master and Doctoral students has been largely for programs in this area. David's Unit also enjoys a very good relationship with an international expert Craig Bamworth in the social media area who has kindly agreed to offer his expertise to Bruce (the program manager).

One of the projects within the Social Media Research Centre larger project that Bruce has identified as important is the development of a web application for the proposed centre.

This application would include an internet website and section for members on the intranet. Bruce has appointed You as the manager of this project commencing work on 1 April 2017. Bruce's team has conducted the feasibility study and financial analysis to confirm that project must go ahead and must commence as you join your role.

You must assist Bruce in preparing the project charter that need to be submitted within first week of May 2017 via a kick-off meeting to be held with all major stakeholders presenting and discussing the charter before they all signoff and approve charter.

This website should contain information about the major research projects, list of supervisors, Masters and PhD student projects, publications (conference and journal papers), and project reports. The application manager Sonia Reed should update all these details on the website using the intranet login. Members can also update their project details via their member account. It has also been identified by Bruce that displaying the information, program, recorded presentations and reports/publications of the events held in the area of social media research will help in promoting the centre. Sonia would collect this information from the events manager and update the information on the web application before, during and after the events as needed.

Your team must include appropriate experts to assess the application, network and database software and hardware needs to support this project.

Your manager, Bruce has given you guidance that the project needs to be completed within 8 months and that costs should be minimised wherever possible with given budget of AUD 50000.00

Task 1: Prepare Project Charter as per below template

Basic details Including: Title of the project, Name and email of the Project Manager (yourself), Duration of the project, and High level budget

Project Objectives
o Clear, concise reasoning for why the project is being performed
o Clear, concise definition of what the project's activities will entail ( high level scope)
o Brief description of primary deliverable(s)
o Clear description of the project's benefits to the organisation
o Recognition and description of any limits that the project will not cover and address
MOV - Measurable Organisational Value

(This is the goal of the project and is utilised to define the value that your team project will bring to your client)
Identify the desired area of impact - Rank the following areas in terms of importance: Strategy / Customer / Financial / Operational / Social

With reference to your project, identify one or two of the following types of value:
- Better - is improving quality important to your client?
- Faster - does your client want to increase efficiency?
- Cheaper - is cutting costs important?
- Do more - does your client want to continue its growth?

Develop an appropriate metric - this sets the target and expectation of all the stakeholders. It is important to determine a quantitative target that needs to be expressed as a metric in terms of an increase or decrease of money. ( 5 Bullet Points)
(Note: the MOV should inform everyone what the project will achieve, not how it will be achieved. It should also focus on the organisation, not on the technology that will be used to build or support the information system).

Acceptance Criteria
o Identification of specific factors against which the project can be compared to determine success/failure
o Identification of specific deliverables for the project as a whole
o Inclusion of due dates for the deliverables
o Clear identification of milestone and milestone exit points
o Factors should include a specific metrical comparison

Assumptions and Constraints
o Any assumptions made during the course of the project
o List of constraints that entail the limitations that are required to be addressed

Stakeholder List
o Complete list of stakeholders including the sponsor, PM, executive members and few important members that are required to contribute to high level decisions

Lessons Learned
o Identification of pitfalls to be avoided, based on the past projects and experience
o Evidence of thought as to what can and cannot affect the project in terms of how the project will run

Charter Sign off
o This section should include the stakeholders signing off the charter for commitment.
o Some key stakeholders must comment make comments

Task 2: Prepare Communications Plan as per the template given

Communication Plan Template

- Plan purpose - A brief description of why and how the plan was developed, and an overview of the overall team communication philosophy. Also states types of communications planned, for lateral, downward, and upward communication.

- Identification of stakeholders - The "who" in the project that requires information, (i.e. team members, project sponsor, class professor, etc.) and also the responsible parties to receive and/or communicate information.

- Information to be shared - The "what" in terms of project information communication. Describes types of information that the team uses to communicate amongst its own project members, and also to the sponsor

- Frequency of information exchange - The "when" describes how often communications will be held (i.e. daily, weekly, monthly, as needed, etc.)

- Location of information exchange - The "where" states the location of the meeting or other interactions

- Purpose of communication - The "why" description assures that communications are held effectively.

- Mechanism for communication - The "how" describes the media for communication (i.e. physical meeting, email, phone, message group, etc.)

- Change management - Description on how the team will handle changes in the project, whether it is in terms of project scope, schedule, or resources. This includes how the team plans to communicate changes as well as how the team plans to make decisions about changes.

- Meeting agenda - Gives a brief overview of what the team plans to accomplish in each of its meetings, how it documents goals and objectives for meetings, and defines and assigns actions for the team to accomplish project objectives.

Rationale

This assessment task covers first four topics and has been designed to ensure that you are engaging with the subject content on a regular basis. More specifically it seeks to assess your ability to:

o Identify the responsibilities of a Project manager when participating in a real world project;

o Define the role of management in projects, particularly from the view point of the practitioner as a member of the project team;

o Apply project management skills, methods, techniques and tools to a real world problem typical of a project manager;

o Explain areas of knowledge relevant to project management; and

o Discuss the many problems facing the project manager and to note the "best practices" being utilised in order to produce effective, efficient and quality projects on time and within budget

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92478844
  • Price:- $65

Priced at Now at $65, Verified Solution

Have any Question?


Related Questions in Project Management

What are the advantages and disadvantages of cost of poor

What are the advantages and disadvantages of Cost of Poor Quality (COPQ)?

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

Project investment analysis assignment -the aim of this

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have bee ...

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

Define quality management philosophy and identify which

Define quality management philosophy and identify which quality guru worked with Toyota to make it a success?

In software development and design how are requirement

In software development and design how are requirement documents used and maintained, especially as requirements evolve? Also, what processes, methods, and techniques are available for maintenance, and how effective are ...

Advanced topics in project management assignment -outline -

Advanced Topics in Project Management Assignment - Outline - Project management is a highly regarded discipline in engineering. It experienced a number of changes or "natural evolution" in the last century, influenced by ...

Leading lean projects assessment case study - continuous

Leading Lean Projects Assessment Case study - Continuous Improvement Introduction - Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the t ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year