A project has the activities, precedence relationships, and time estimates in days which are given below:

Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6

find out latest finish, earliest start, earliest finish, latest start,and slack for each activity

Determine the critical path and duration of project?

Find the probability that project will take longer than 38 days?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932369

Have any Question?


Related Questions in Project Management

Check all of the following that arenbsptrue for top-down

Check all of the following that are  true for top-down estimates (when being compared with bottom-up estimates). Make sure your answer reflects what is correct for  Top-Down Estimates .  Lower cost to create estimate Hig ...

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

1 what are some benefits and values of scheduling software

1) What are some benefits and values of scheduling software in a project schedule?

Read the microsoft word document and do the following1 a

Read the Microsoft word document and do the following. 1. A list of resources that will be used to complete the project plan, 2. The initial bibliography Attachment:- PROJECT PROPOSAL.rar

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Case study and research project clairicationfinding a case

Case Study and Research Project Clairication Finding a case for the research project does not mean that you are limited to the company identified in the case. Rather it is to identify an issue identified in the case that ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Mikes tees a relatively large company that prints t-shirts

Mike's Tees, a relatively large company that prints T-shirts, is developing a system that allows customers to upload their image files on a server and have them printed on T-shirts. The project was drafted and planned to ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As