A project has the activities, precedence relationships, and time estimates in days which are given below:

Activity Predecessor Optimistic Most likely Pessimistic
Activities Time Time Time
A -- 6 7 8
B A 4 4 4
C A 5 6 8
D B 8 10 10
E B 7 10 15
F C 9 9 13
G C 7 7 7
H D 4 6 8
I E, F 6 9 11
J G 8 9 10
K H, I, J 3 5 6

find out latest finish, earliest start, earliest finish, latest start,and slack for each activity

Determine the critical path and duration of project?

Find the probability that project will take longer than 38 days?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M932369

Have any Question? 

Related Questions in Project Management

Mike and iris were reviewing the asset valuation worksheets

Mike and Iris were reviewing the asset valuation worksheets that had been collected from all the company managers. "Iris," Mike said after a few minutes, "the problem, as I see it, is that no two managers gave us answers ...

The mens department of a large store employs one tailor for

the men's department of a large store employs one tailor for customer fitting, the number of customers requiring fitting appear to follow a poison distribution with mean arrival rate of 24per/hr, customers are fitted on ...

Assignmentpart 1schedulingfor an organization the following

Assignment: PART 1 Scheduling For an organization, the following project schedule is given. Assume that all times are in days. Task Predecessor Normal Time Crash Time Crash Cost Slope A None 7 7 NA B A 3 3 NA C A 8 4 600 ...

1 a company typically has many systems it wants to build

1. A company typically has many systems it wants to build, but unfortunately it usually doesn't have the resources to build all the systems. How does a company decide which systems to build? 2. How do the four implementa ...

The information age in which you livechanging the face of

The Information Age in Which You Live Changing the Face of Business OPENING CASE STUDY: IS YOUR SOCIAL SECURITY NUMBER WORTH $98? The answer for many people is yes. But they're not referring to the worth of their own soc ...

Project management skills and formal and informal project

"Project Management Skills and Formal and Informal Project Management" Please respond to the following: • Speculate on the main reasons why the skills and training of project managers have changed over time. Give your op ...

Projectoverviewdevelop a microsoft excel application that

Project overview Develop a Microsoft Excel application that provides support for decision making. The application must be useful to someone, which means it needs to help someone analyze data and make appropriate decision ...

1 why can the process of commercialization take a

1. Why can the process of commercialization take a considerable amount of time? 2. What is product differentiation, and how can it be achieved? 3. Explain how the term quality has been used to differentiate products in t ...

Part a project schedule1in assignment you developed a

Part A: Project Schedule 1. In Assignment, you developed a project plan. Now, using the information from your project proposal, create a multi-level work breakdown structure (WBS) and detailed project schedule. Your proj ...

Discussionagile schedule development gradedas we have seen

DISCUSSION Agile Schedule Development (graded) As we have seen, traditional and Agile schedule developments are quite different. Agile project management was originally developed to do software development. Could a tradi ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

WalMart Identification of theory and critical discussion

Drawing on the prescribed text and/or relevant academic literature, produce a paper which discusses the nature of group

Section onea in an atwood machine suppose two objects of

SECTION ONE (a) In an Atwood Machine, suppose two objects of unequal mass are hung vertically over a frictionless

Part 1you work in hr for a company that operates a factory

Part 1: You work in HR for a company that operates a factory manufacturing fiberglass. There are several hundred empl

Details on advanced accounting paperthis paper is intended

DETAILS ON ADVANCED ACCOUNTING PAPER This paper is intended for students to apply the theoretical knowledge around ac

Create a provider database and related reports and queries

Create a provider database and related reports and queries to capture contact information for potential PC component pro