Question 1:

Consider the following table and answer the questions that follow

Activity

Description

Predecessor

Optimistic time in days

Most likely time in days

Pessimistic time in days

A

Position recruiting

-

5

8

17

B

System development

-

3

12

15

C

System training

A

4

7

10

D

Equipment training

A

5

8

23

E

Manual system test

B,C

1

1

1

F

Preliminary  system

change over

B,C

1

4

13

G

Computer personnel interface

D,E

3

6

9

H

Equipment
modification

D,E

1

2.5

7

I

Equipment testing

H

1

1

1

1

System     debugging

and installation

F,G

2

2

2

K

Equipment changeover

1,1

5

8

11

1.1 Determine the expected activity times

1.2 Develop an activity on arrow network diagram (AOA)

1.3 Determine the earliest start and finish times; and the latest start and finish time

1.4 Determine the critical path

1.5 Determine the expected project duration

Question 2:

CASE STUDY: Project Charter; Payroll Project.

Authorising the Project

This Charter formally authorizes the Payroll Project to develop and implement a new payroll system for use in Jones Consulting Company's payroll group. A project plan will be developed and submitted to the Project Sponsor for approval. The project plan will include: scope statement; schedule; cost estimate; budget; and provisions for scope, resource, schedule, communications, quality, risk, procurement, and stakeholder management as well as project control. All resources will be assigned by the Project Sponsor, Van Johnson, human Resources Director.

Project Scope:

State the scope of the project, its deliverable and what business needs, problems or opportunities the project addresses - a market demand, business need, legal requirement, social need, customer request or technological advance. The purpose of the Payroll project is to improve the timeliness and accuracy of payroll operations. This project meets Jones Consulting's need for improved efficiencies across all departments by reducing payroll cycle time and minimizing staffing required for payroll operations.

The project deliverables shall include: Payroll system design, all coding, testing and implementation of an integrated system for use with existing IT infrastructure and a user guides. The objectives of the Payroll project are: To reduce payroll cycle time by 30% and reduce payroll staffing by 20%. High level risks for this project include: Ensuring implementation is completed without impacting ongoing payroll operations and ensuring there are no issues with migrating payroll accounts from the legacy system to the new system. Success will be determined by the Project Sponsor once the system is implemented and one full payroll cycle has been completed that meets the objectives with no discrepancies.

The Project Manager

The Project Manager, Bill Smith, is hereby authorized to interface with management as required, negotiate for resources, delegate responsibilities within the framework of the project, and to communicate with all contractors and management, as required, to ensure successful and timely completion of the project. The Project Manager is responsible for developing the project plan, monitoring the schedule, cost, and scope of the project during implementation, and maintaining control over the project by measuring performance and taking corrective action.

Milestones

The project plan will be submitted and approved in accordance with the milestone schedule below. Upon approval of the project plan resources will be assigned to the project and work will commence within 5 business days. The Project Sponsor must approve any schedule changes which may impact milestones. A detailed schedule will be included in the project plan. The high level milestone schedule is:

Feb 1, 2015 - Project Plan Complete and Approved
Mar 31, 2015 - Payroll Design Completed
May 31, 2015 - Coding Completed
June 30, 2015 - Testing Completed
July 31, 2015 - Beta Testing Completed
Sept 30, 2015 - Implementation Completed
Oct 15, 2015 - One Payroll Cycle Complete and Project Completion

Paragraph 5: Project Budget

The budget for the Payroll project is R420,000. It is to be funded through the FYxx Human Resources Technology Budget.

SPONSOR ACCEPTANCE

Approved by the Project Sponsor:
Date:
Project Sponsor Name
Project Sponsor Title

Use the following checklist to compile a project scope statement.

From the Project charter above create a detailed scope statement. Use the following scope checklist:

1. Objectives
2. Deliverables
3. Milestones
4. Technical requirements
5. Limits and exclusions

Question 3:

3.1 Formulate at least five risks and associated impacts based on your scope statement developed in question 2 above.

3.2 With motivation, score the risks on a quantitative risk assessment template.

3.3 Create a risk management plan for all the formulated risks

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91368791
  • Price:- $160

Guranteed 48 Hours Delivery, In Price:- $160

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As