Assignment

You have kicked off the District 4 Production Warehouse Move project, your contractors are in place and working on receiving the proper building permits.

You originally were told the permits would only take 2 weeks to obtain but the contractors are telling you it will now take 3 weeks. You need to build the additional week into your schedule for each permit that will be obtained.

In addition, your framing and drywall contractors have just told you they are running late on their other jobs and can only release half their crew for your project. This will double their schedule.

Build the extra time into your schedule by doubling the installation work timelines for both the framing and drywall. Your project plan should also be updated with the new 3-week timeline for obtaining permits. Use the project plan you created for this task.

You are now looking at an extended project delivery date. Your project sponsor was very clear that you must be done in a 4 month timeframe so you will need to look at options for reducing your schedule to fit into the 4 month window.

You have an option of hiring another contractor to help with the framing and drywall work but it will increase your budget by $200,000.

Determine your best course of action for bringing this project in on schedule and update your project plan to reflect your recommendation. Develop a 5-6 slide presentation for senior management outlining your proposed solution. You are seeking approval to proceed with your new plan.

Attachment:- Project-Plan.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92563616
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Project Management

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

This is the brief for the third and final exercise for this

This is the brief for the third and final exercise for this project. Your group has been appointed as Project Manager by The Proprietary Very Limited Corporation (PVLC) to carry out development and feasibility analyses o ...

Assignment 1 the core values and principlesplease have the

Assignment 1: The Core Values and Principles Please have the following titles and include content as per assignment instructions under each paragraph: History of Agile project management. Philosophy and purpose of Agile ...

What are the types of documents required to define

What are the types of documents required to define parameters in a project?

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

As a project manager answer these questions1 a how does the

As a project manager answer these questions, 1) a. How does the weighted scoring approach avoid the drawbacks of the NPV approach? b. Can the two approaches be combined? if so How? How are you going to apply this piece o ...

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As