1. Risk Likelihood

A product improvement project involves an existing product (M), with minor complexity (C), and is dependent for schedule on an existing system (D). Therefore,

M = 0.1, C = 0.3, D = 0.3

(as reference Risk Assessment Calculations document, Likelihood table).

Consider that criteria are weighted as follows:

M is (0.5), C is (0.3), D is (0.2), therefore W1 = 0.5, W2 = 0.3, W3 = 0.2

Calculate the Composite Likelihood Factor (CLF).

2. Risk Impact

A product test failure is expected to have a minor impact on overall technical performance and be correctable within 2 months at a cost of 10 percent. Therefore,

TI = 0.3, CI = 0.5, SI = 0.5

(as per reference Risk Assessment Calculations document, Impact table).

Consider that criteria are weighted as follows:

TI is Moderate (0.5), CI is Minor (0.3), SI is Low (0.2) therefore W1 = 0.5, W2 = 0.3, W3 = 0.2

Calculate the Composite Impact Factor (CIF).

3. Risk Consequence Rating

Use the previous problems (#1 Risk Likelihood and #2 Risk Impact) and calculate the Risk Consequence Rating (RCR).

5. Risk Time (RT), Risk Cost (RC), Expected Time (ET), Expected Cost (EC). Critical Path (L - V - R - C)

WBS Element

Critical Path (CP)

BEC

BTE
(Week)

Corrective Cost

Corrective Time (Week)

Likelihood

L

CP

$20,000

9

$4,000

2

0.2

V

CP

$16,000

8

$4,000

2

0.3

T

 

$32,000

5

$8,000

2

01

U

 

$20,000

7

$12,000

3

0.2

S

 

$15,000

3

$4000

1

0.3

J

 

$126000

3

$4,000

1

0.1

R

CP

$10,000

4

$4,000

3

0.3

C

CP

$15,000

6

$5,000

2

0.3

 

$147,000

27

 

BCE = total cost
BTE = total duration based on critical path

Below is a table with calculated Risk Time (RT) and Risk Cost (RC) for all the WBS elements (individual values and total values). These calculations are based on the information in the table above.

WBS
ELEMENT

RC in dollars
(corrective time x likelihood)

RT in weeks
(corrective time x likelihood)

L

$800

0.4 weeks    CP

V

1,200

0.6               CP

T

80

0.2

U

2,400

0.6

S

1,200

0.3

J

400

0.1

R

1,200

0.9              CP

C

1,500

0.6              CP

TOTAL

$8,780.00

3.7(CP = 2.5)

Given the information in the tables above. Hint: Use the critical path for RT (L - V - R - C_ .

a) What is the project expected cost (EC) for the total project?
b) What is the project expected time (ET) for the total project?

4. Decision Tree

An author decides to write a book. Historical data indicates that if the market is strong, gross sales will be $1 Million. If the market is weak, the gross sales will be only $50,000. There is a 70% chance of a strong market and a 30% chance of a weak market.

The author must decide whether to use a publisher or self-publish the book himself. If he self-published the book, all the sales go to himself as the author. If he uses a published, the publisher will receive 10% royalty on sales.

The decision tree for the problem is shown below. Determine:

a) The expected value for the publisher branch/option.

b) The expected value for the self-publishing branch/option.

c) Which branch/option should the author take?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91753526

Have any Question?


Related Questions in Project Management

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

How does developing interpersonal skills enhance individual

How does developing interpersonal skills enhance individual and team performance

This is the brief for the third and final exercise for this

This is the brief for the third and final exercise for this project. Your group has been appointed as Project Manager by The Proprietary Very Limited Corporation (PVLC) to carry out development and feasibility analyses o ...

Your essay should be a properly constructed academic essay

Your essay should be a properly constructed academic essay of 5,000 words. It should contain an effective introduction, body and conclusion. The introduction should introduce the essay and include your argument. The body ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Define quality management philosophy and identify which

Define quality management philosophy and identify which quality guru worked with Toyota to make it a success?

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

Part -1 define project and develop planperformance

Part -1 Define project and develop plan Performance objective Candidates will demonstrate knowledge and skills required to define projects and develop project plans. Assessment description Using the workplace scenario in ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As