1. Risk Likelihood

A product improvement project involves an existing product (M), with minor complexity (C), and is dependent for schedule on an existing system (D). Therefore,

M = 0.1, C = 0.3, D = 0.3

(as reference Risk Assessment Calculations document, Likelihood table).

Consider that criteria are weighted as follows:

M is (0.5), C is (0.3), D is (0.2), therefore W1 = 0.5, W2 = 0.3, W3 = 0.2

Calculate the Composite Likelihood Factor (CLF).

2. Risk Impact

A product test failure is expected to have a minor impact on overall technical performance and be correctable within 2 months at a cost of 10 percent. Therefore,

TI = 0.3, CI = 0.5, SI = 0.5

(as per reference Risk Assessment Calculations document, Impact table).

Consider that criteria are weighted as follows:

TI is Moderate (0.5), CI is Minor (0.3), SI is Low (0.2) therefore W1 = 0.5, W2 = 0.3, W3 = 0.2

Calculate the Composite Impact Factor (CIF).

3. Risk Consequence Rating

Use the previous problems (#1 Risk Likelihood and #2 Risk Impact) and calculate the Risk Consequence Rating (RCR).

5. Risk Time (RT), Risk Cost (RC), Expected Time (ET), Expected Cost (EC). Critical Path (L - V - R - C)

WBS Element

Critical Path (CP)

BEC

BTE
(Week)

Corrective Cost

Corrective Time (Week)

Likelihood

L

CP

$20,000

9

$4,000

2

0.2

V

CP

$16,000

8

$4,000

2

0.3

T

 

$32,000

5

$8,000

2

01

U

 

$20,000

7

$12,000

3

0.2

S

 

$15,000

3

$4000

1

0.3

J

 

$126000

3

$4,000

1

0.1

R

CP

$10,000

4

$4,000

3

0.3

C

CP

$15,000

6

$5,000

2

0.3

 

$147,000

27

 

BCE = total cost
BTE = total duration based on critical path

Below is a table with calculated Risk Time (RT) and Risk Cost (RC) for all the WBS elements (individual values and total values). These calculations are based on the information in the table above.

WBS
ELEMENT

RC in dollars
(corrective time x likelihood)

RT in weeks
(corrective time x likelihood)

L

$800

0.4 weeks    CP

V

1,200

0.6               CP

T

80

0.2

U

2,400

0.6

S

1,200

0.3

J

400

0.1

R

1,200

0.9              CP

C

1,500

0.6              CP

TOTAL

$8,780.00

3.7(CP = 2.5)

Given the information in the tables above. Hint: Use the critical path for RT (L - V - R - C_ .

a) What is the project expected cost (EC) for the total project?
b) What is the project expected time (ET) for the total project?

4. Decision Tree

An author decides to write a book. Historical data indicates that if the market is strong, gross sales will be $1 Million. If the market is weak, the gross sales will be only $50,000. There is a 70% chance of a strong market and a 30% chance of a weak market.

The author must decide whether to use a publisher or self-publish the book himself. If he self-published the book, all the sales go to himself as the author. If he uses a published, the publisher will receive 10% royalty on sales.

The decision tree for the problem is shown below. Determine:

a) The expected value for the publisher branch/option.

b) The expected value for the self-publishing branch/option.

c) Which branch/option should the author take?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91753526

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year