QUESTION 1
Failure to quantify project objectives raises the risk that the project won't achieve the?

Statement of work

Project plan

Customer's expectations

Project control

QUESTION 2
How do we know if the project is successful. One aspect is validating scope. Scope validation is the process of the project customer accepting?

Project deliverables

Project scope

Project WBS

Project inspection

QUESTION 3
The change control system should do several things for the project management team including document all change requests, track each change requests document approval levels required for change, and

Restate scope requirements

Indicate how change impacts communications

Provide the status of each change request

How change impacts quality

QUESTION 4
The approach maps ideas to show the relationship among requirements and the difference between requirements.

Mind Mapping

Context Diagram

Network Diagram

Funding limits

QUESTION 5
These diagram shown the relationship between elements of an environment.

Mind Mapping

Context Diagram

Network Diagram

Funding limits

QUESTION 6
There are seven key processes associated with project time management.
The seven processes are interdependent on one another and on the _________ of the project?

Schedule

Activities

Estimations

Life cycle

QUESTION 7
The planning technique that focuses on the immediate while considering the big picture and utilizes iterations of planning is called?

Waterfall method

Rolling wave

Agile project management

Scrum

QUESTION 8
Part of the process of sequencing events is the development of network diagrams. A network diagram shows the relationship of the work activities and how the activities progress start to finish. What is the most common method for arranging work visually into a network diagram?

Activity on node

Activity on arrow

Precedence diagramming method

Activity sequencing

QUESTION 9
These dependencies are the natural order of activities.

Mandatory dependencies

Discretionary dependencies

External dependencies

Internal dependencies

QUESTION 10
What is the most accurate project estimating methods for time and cost?

Published estimating data

Bottom-up estimating

Parametric estimating

Sequencing estimation.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92661839
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As