Assignment:

PART 1

Scheduling

For an organization, the following project schedule is given. Assume that all times are in days.

Task

Predecessor

Normal Time

Crash Time

Crash Cost Slope

A

None

7

7

NA

B

A

3

3

NA

C

A

8

4

600

D

A

4

4

NA

E

B

6

5

600

F

C, D

2

2

NA

G

E, F

6

6

NA

H

F

5

3

400

I

G, H

4

4

NA

J

I

2

2

NA

In a 2 page Microsoft Word document, address the following:

Draw the AON project network using Microsoft Project, Microsoft Visio, or some other tool capable of creating such a network. Perform a critical path analysis for the network and calculate the ES, EF, LS, and LF times. Calculate the slack time for each activity. Identify the critical path. Assume that the organization will receive a $400 bonus for each day the duration of the project is shortened. The organization is also responsible for paying the crash cost associated with shortening the schedule. To maximize the net profit, identify which task you should crash and by how much. Support your responses with examples.

PART 2 Forecasting

Select a product that you can purchase at a grocery store or at a discount retailer and respond to the following:

Identify the factors that would impact the demand for the product that you have selected. If you wish to develop a forecast of the demand for this product in a future month (or for other appropriate time period), identify what type of forecasting method would be appropriate. Identify the variables for which you would need values to be able to calculate an actual forecast for a future month (using the forecasting method you selected). Create an equation that you believe would accurately predict the demand for this product in a future month and solve the equation to derive a forecast for this product in the future month that you had selected.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92086715
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Project Management

Your essay should be a properly constructed academic essay

Your essay should be a properly constructed academic essay of 5,000 words. It should contain an effective introduction, body and conclusion. The introduction should introduce the essay and include your argument. The body ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

Define a strategic information system give two examples of

Define a strategic information system. Give two examples of these systems

Case study and research project clairicationfinding a case

Case Study and Research Project Clairication Finding a case for the research project does not mean that you are limited to the company identified in the case. Rather it is to identify an issue identified in the case that ...

In software development and design how are requirement

In software development and design how are requirement documents used and maintained, especially as requirements evolve? Also, what processes, methods, and techniques are available for maintenance, and how effective are ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

What methods could a project manager use to resolve

What methods could a project manager use to resolve resource overloads?

Wahat are the similarities and differences between the

Wahat are the similarities and differences between the PMBOK and PRINCE2 approaches to project Stackholder management.

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As