Assignment

 

You are 5 months into a 10 month project. The project is linear, which means that the planned progress and budgeted spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 5:

 

Actual cost to date = $100,000
Planned value of work scheduledto date = $120,000

 

The CFO is excited and has sent you an email congratulating you for being 17% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we ‘really' doing? To understand the true project performance, we need to apply earned value techniques.

 

Since we have the AC and the PV the missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 9 tasks scheduled to be complete have actually been completedby the end of month 5. Task 7 isn't even started! This information gives you the final data you need to apply ‘Earned Value'and develop an objective analysis.

 

Careful. Be sure to read the problem carefully and don't make assumptions that are not given in the problem.

 

1. What are the PV, EV, and AC for the project at the end of month 5?

 

 

2. What are the SV, CV, SPI, and CPI for the project?

 

 

3. Assess the project performance to date? Do you get to have the celebration?

 

5-2 Earned Value Calculation

 

Your project has four activities. Below is the current status of each activity.

 

Activity A was to have cost $160,000 when complete. Its costs so far are $95,000. It is 45% complete.

 

The activity has completed 5 weeks of a planned 8-week schedule.

 

Activity B is finished. It finished 2 weeks late. It cost $135,000. And it was planned to have cost $130,000.

 

Activity C is at the end of week 4 of a planned 8-week effort. It is 40% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

 

Activity D is at the end of week 3 of a planned 6-week schedule. It has cost $110,000 so far. It was estimated to cost $200,000 when finished. It is approximately 50% complete.

 

Using this data, calculate the following.

 

1. What are the PV, EV, and AC for each of the activities and the complete project?

 

 

EV

PV

AC

A

 

 

 

B

 

 

 

C

 

 

 

D

 

 

 

Project

 

 

 

 

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

 

 

SV

CV

SPI

CPI

A

 

 

 

 

B

 

 

 

 

C

 

 

 

 

D

 

 

 

 

Project

 

 

 

 

 

3. Assess the project performance to date? Do you get to have the celebration?

 

You should focus on the total project but look at the individual activities that have major effects.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92486199
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Project Management

What is fast tracking and its impact on the project as it

What is fast tracking and its impact on the project as it relates to project management

What is the current state or condition of information

What is the current state or condition of Information Technology Project Management? What are the challenges and complexities faces by many IT Project Managers of today?

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

42908 assessment task - project proposal1 executive summary

42908 Assessment Task - Project Proposal 1. Executive Summary - Brief overview of project, main aim of project, potential findings and conclusions. 2. Introduction - Presents general project area, relevance of project, s ...

In software development and design how are requirement

In software development and design how are requirement documents used and maintained, especially as requirements evolve? Also, what processes, methods, and techniques are available for maintenance, and how effective are ...

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

The hospitality industry comprises diverse and varied

The hospitality industry comprises diverse and varied functions and scale of operations. Some organisations may be single function business enterprise such as catering organisation. Others may be larger with multiple bus ...

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

Project investment analysis assignment -the aim of this

PROJECT INVESTMENT ANALYSIS ASSIGNMENT - The aim of this project is to introduce participants to concepts of Financial Feasibility Modelling and the use of spreadsheets for feasibility exercises. Assume that you have bee ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As