Assignment

 

You are 5 months into a 10 month project. The project is linear, which means that the planned progress and budgeted spending occurs at a constant rate. Our crack project team of highly skilled associates has worked diligently and put in extra hours to keep the project going. Our accounting department has provided the following data at the end of month 5:

 

Actual cost to date = $100,000
Planned value of work scheduledto date = $120,000

 

The CFO is excited and has sent you an email congratulating you for being 17% under budget. However, is it really time to hold a team celebration? That would be fun but your project manager mentality kicks in. Those numbers look good but how are we ‘really' doing? To understand the true project performance, we need to apply earned value techniques.

 

Since we have the AC and the PV the missing piece we need is Earned Value (i.e. what we have actually accomplished so far). You meet with your team and find that only 6 of the 9 tasks scheduled to be complete have actually been completedby the end of month 5. Task 7 isn't even started! This information gives you the final data you need to apply ‘Earned Value'and develop an objective analysis.

 

Careful. Be sure to read the problem carefully and don't make assumptions that are not given in the problem.

 

1. What are the PV, EV, and AC for the project at the end of month 5?

 

 

2. What are the SV, CV, SPI, and CPI for the project?

 

 

3. Assess the project performance to date? Do you get to have the celebration?

 

5-2 Earned Value Calculation

 

Your project has four activities. Below is the current status of each activity.

 

Activity A was to have cost $160,000 when complete. Its costs so far are $95,000. It is 45% complete.

 

The activity has completed 5 weeks of a planned 8-week schedule.

 

Activity B is finished. It finished 2 weeks late. It cost $135,000. And it was planned to have cost $130,000.

 

Activity C is at the end of week 4 of a planned 8-week effort. It is 40% complete. It was to cost $100,000 when finished. Its costs to date are $50,000.

 

Activity D is at the end of week 3 of a planned 6-week schedule. It has cost $110,000 so far. It was estimated to cost $200,000 when finished. It is approximately 50% complete.

 

Using this data, calculate the following.

 

1. What are the PV, EV, and AC for each of the activities and the complete project?

 

 

EV

PV

AC

A

 

 

 

B

 

 

 

C

 

 

 

D

 

 

 

Project

 

 

 

 

2. What are the SV, CV, SPI, and CPI for each of the activities and the complete project?

 

 

SV

CV

SPI

CPI

A

 

 

 

 

B

 

 

 

 

C

 

 

 

 

D

 

 

 

 

Project

 

 

 

 

 

3. Assess the project performance to date? Do you get to have the celebration?

 

You should focus on the total project but look at the individual activities that have major effects.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92486199
  • Price:- $35

Priced at Now at $35, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As