Assignment: Performing Effective Project Monitoring and Risk Management

Imagine that you are employed as an IT project manager by a prestigious coffeemaker organization. This organization operates many coffee shops within the region and would like to promote its brand by creating a mobile application that will provide its customers with the ability to view the nearest coffee shop location within their geographical area.

As a member of the software development team, you estimate a total project cost of $150,000. You have designated control points to measure project progress. At control point 2, the following data is available:

Budget Cost of Work Performed

$ 24,000

Actual Cost of Work Performed

$ 27,500

There are various stakeholders that are interested in the progress of the project. These stakeholders include the marketing management team (internal customers), software designers, programmers, testers, and upper management. The software development team has attempted to release a mobile application of this magnitude in the past; however, lack of sponsorship, mobile development expertise, and technical infrastructure has limited the team's success.

Write a four to six (4-6) page paper in which you:

Identify at least four (4) attributes of the mobile application development project that can be measured and controlled and evaluate how each is a critical factor for the success of the project.

Generate a project plan summary of the various project milestones. Develop a WBS that details work packages required to complete project scope.

Develop a workflow model that can be used to inspect and detect defects during the acceptance of this mobile product through the use of graphical tools in Microsoft Word or Visio, or an open source alternative such as Dia. Note: The graphically depicted solution is not included in the required page length.

Describe how the defects detected during the acceptance of the mobile application should be reported and explain the circumstances in which a defect may not require reporting.

Analyze the communication needs of the different project stakeholders. Explain the types of project status reports that would be useful to each.

Compute the cost variance, schedule variance, cost performance index, schedule performance index, and estimated actual cost using the information presented at control point 2. Interpret the project schedule and budget status from the calculations.

Explain how work package, binary tracking, and earned valued reporting can be used effectively during the maintenance phase of the software life cycle if various change requests may be assigned to individuals and processed on an individual basis.

Develop a risk register that will document all of the estimated risks. Assign one (1) risk management technique for each risk and explain the basis for your selection.

Use at least three (3) quality resources in this assignment.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91326920
  • Price:- $40

Guranteed 36 Hours Delivery, In Price:- $40

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As