Assignment: A Gantt Chart Based Crashing

You are considering whether or not to crash project activities to expedite your project. You have calculated the costs per activity for both normal and crashed options. Your assignment is twofold: create a Gantt chart based on the data in the table below and answer the questions that follow. Your Gantt chart should include all project activities, task information, duration, and cost variables as well as a project title and date.

This assignment can be completed using project management software (MS Project, ProjectLibre, Open Project, etc.) or other appropriate application software. While most project management applications do a lot of these tasks automatically, if you are using other application software you may need to develop the components separately. Thus, you will need to input the data from table below; then identify the critical path as well as a graphical depiction of a Gantt chart that highlights the critical paths that you have prioritized as candidates for crashing. Include your Gantt chart in your paper as an appendix, which can be referenced for addressing the assignment questions.


Normal

Crashed

Activity

Duration

Costs

Duration

Costs

A

4 Days

$1,000

3 Days

$2,000

B

5 Days

$ 2,500

3 Days

$5,000

C

3 Days

$  750

2 Days

$1,200

D

7 Days

$3,500

5 Days

$5,000

E

2 Days

$500

1 Days

$3,000

F

5 Days

$2,000

4 Days

$3,000

G

9 Days

$4,500

7 Days

$6,300

Answer the following questions in your assignment:

1. Which activities are the most likely candidates for crashing (i.e., which are the most cost-effective to crash) and why?

2. Using the critical path from this activity network, consider A - C - D - F as the critical path and assume all other paths are less than fully crashed. Prioritize the candidates for crashing.

3. How does the critical path from activity network change the decision rule?

Submit a two- to three-page paper with the answers to the above questions in addition to your Gantt chart. The paper must include an introduction and conclusion. Inset your Gantt chart depiction as appendices in your paper. Include a titlepage and a reference page that includes at least two outside references (one of which may include your textbook) to support your responses.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92530304
  • Price:- $45

Priced at Now at $45, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As