This Assignment will differ from other Assignments you have completed in the past. The key difference is you will leverage the POM-QM for Windows software in order to resolve your real-world scenarios. In line with the topics for Week 6, you will focus on solving linear programming and project management problems.

To complete this Assignment:

POM-QM for Windows software

For this part of this project, you will need to use the POM software:

1. Read Appendix IV of the Operations Management (Heizer and Render, 2014) textbook.

2. Review the linear programming section from the POM manual:

Weiss, H.J. (2013) POM-QM for Windows manual. Upper Saddle River, NJ: Prentice Hall. Available from the 'Help' menu in the POM-QM Windows software. (Accessed: 30 December 2014).

You may also wish to research and review online tutorials regarding the linear programming module and/or view the following resource.
Valverde, R. (2014) QM for Windows linear programming [Online] YouTube.

3. Install and launch the POM-QM for Windows software. From the main menu, select Module and then Linear Programming.

4. Program the linear programming formulation for the problem below and solve it with the use of POM. Refer to Appendix IV from the Heizer and Render (2014) textbook.

Note: Do not program the non-negativity constraint, as this is already assumed by the software.

For additional support, please reference the POM-QM for Windows manual available from the 'Help' menu in the POM-QM Windows software.

Individual Project, part 1

A firm uses three machines in the manufacturing of three products:

• Each unit of product 1 requires three hours on machine 1, two hours on machine 2 and one hour on machine 3.

• Each unit of product 2 requires four hours on machine 1, one hour on machine 2 and three hours on machine 3.

• Each unit of product 3 requires two hours on machine 1, two hours on machine 2 and two hours on machine 3.

The contribution margin of the three products is £30, £40 and £35 per unit, respectively.

The following are available for scheduling:

• 90 hours of machine 1 time

• 54 hours of machine 2 time

• 93 hours of machine 3 time

Linear programming and project management

The linear programming formulation of this problem is as follows:

Maximise Z = 30X1 + 40X2 + 35X3

3X1 + 4X2 + 2X3 <= 90 2X1 + 1X2 + 2X3 <=54 X1 + 3X2 + 2X3 <=93 With X1, X2, X3 >= 0

To answer this question:

Answer each question and explain your reasoning or show your calculations.

1. What is the optimal production schedule for this firm? What is the profit contribution of each of these products?

2. What is the marginal value of an additional hour of time on machine 1? Over what range of time is this marginal value valid?

3. What is the opportunity cost associated with product 1? What interpretation should be given to this opportunity cost?

4. How many hours are used for machine 3 with the optimal solution?

5. How much can the contribution margin for product 2 change before the current optimal solution is no longer optimal?

Individual Project, part 2

For this part of this project, you will need to use the POM software:

1. Review the linear programming section from the POM manual:

Weiss, H.J. (2013) POM-QM for Windows manual. Upper Saddle River, NJ: Prentice Hall. Available from the 'Help' menu in the POM-QM Windows software.

You may also wish to research and review online tutorials regarding the linear programming module.

2. Program the project management problem below and solve it with the use of POM. Select Project Management(PERT/CPM) module, and then select the option File->New->Mean, Std dev given items.

Activity

Mean duration

Std. dev. (days)

A

11

0.9

B

13

1.1

C

7

0.2

D

9

0.8

E

6

1

F

7

1.2

G

10

0.7

H

9

0.6

To answer this question:

Answer each question and explain your reasoning or show your calculations.

1. Calculate the project completion time.

2. Indicate the critical path activities.

3. What is the probability of completing this project between 38 and 40 days?

4. What are the slack values for activities C and F? Interpret the meaning of their slack values.

Management Information System, Management Studies

  • Category:- Management Information System
  • Reference No.:- M92565998
  • Price:- $60

Priced at Now at $60, Verified Solution

Have any Question?


Related Questions in Management Information System

Question suppose you and four friends have a band you think

Question : Suppose you and four friends have a band. You think you're pretty good, but you don't have even a college-wide reputation. Would Kickstarter be an effective way to promote your band? Why or why not? An enginee ...

Review the steps of the sdlc explain why quality service

Review the steps of the SDLC. Explain why quality service delivery depends on the execution of the service delivery life cycle. Discuss the aspects of the SDLC that are critical to quality service management. Explain you ...

Research the it security policy used by your university or

Research the IT security policy used by your university or by some other organization you are associated with. Identify which of the topics listed in Section 14.2 this policy addresses. If possible, identify any legal or ...

Need answers to the below questions 12 - 1 page each

Need Answers to the below Questions (1/2 - 1 page each answer) This is of the assigned textbook "Wharton Managing Emerging Technologies" Q1: Clarify any 2 of the variable evaluation approaches for future markets and emer ...

Assignmentprepare a two-page briefing paper 5 to 7

Assignment Prepare a two-page briefing paper (5 to 7 paragraphs) for the senior leadership and corporate board of Red Clay Renovations which addresses planning (what do we need to do?), programming (how will we do it?), ...

Essay question 1state and explain the main useful

Essay Question 1: State and explain the main useful approaches employed to assess future markets for emerging technologies. Essay Question 2: Explain some of the emerging technologies with relevant examples as discussed ...

Management of it systems and projects assignment - work

Management of IT Systems and Projects Assignment - "Work Breakdown Structure & Project Schedules using Microsoft Project" There are two parts to this assignment: Part 1: MS Project Project Title: Dai-Ichi Corporation Aus ...

Question suppose that you buy a 64-bit pc with 4gb of ram

Question Suppose that you buy a 64-bit pc with 4gb of ram. What is the 16-hex-digit of the last byte of installed memory? Please help me understand this. Show work.

In chapter 2 of the text - managing amp using information

In Chapter 2 of the text - Managing & Using Information Systems: A Strategic Approach, the chapter discusses why information systems experience failure often because of organizational strategy. A classic example of this ...

Lab assignment storyboardingcomplete the lab based on the

Lab Assignment : Storyboarding Complete the lab based on the following: Follow the directions below to complete Lab Assignment : 1. Create a storyboard for a four (4) page Website (one (1) home page and three (3) sub pag ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As