Applied Project Management Case Assignments

Assignment 1 -

Using what you learned in Webinar 1 - Getting Started with MS Project, create a new MS Project file (blank file) and name it with your last name and ASMT1 (example: WilsonASMT1) as the file name. Use the Gantt Chart view and enter the tasks, durations, and dependencies from the basic WBS below. For the dates, use the start date of Monday of Module 3. Be sure that each task is auto-scheduled and be certain to include the non-workday "Company Picnic" that will occur on Thursday of Module 3.

Genesis System Upgrade Project WBS 

1. Evaluation & Recommendations (5 Days)

2. Develop Project Charter (10 Days) (Link to 1)

3. Sponsor Review/Approval (2 Days) (Link to 2)

4. Create Preliminary Scope Statement (5 Days) (Link to 3)

5. Determine Project Team (5 Days) (Link to 3)

6. Project Team Kickoff Meeting (1 Day) (Link to 5)

7. Develop Project Plan (10 Days) (Link to 6)

8. Verify & Validate User Requirements (14 Days) (Link to 7) 

9. Design System (14 Days) (Link to 8)

10. Procure Hardware/Software (14 Days) (Link to 9)

11. Install Preliminary System (2 Days) (Link to 10)

12. Test Preliminary System (5 Days) (Link to 11)

13. Install Live System (5 Days) (Link to 12)

14. User Training (2 Days) (Link to 13)

15. Audit Procurement (5 Days) (Link to 14)

16. Document Lessons Learned (2 Days) (Link to 15)

17. Update Files/Records (2 Days) (Link to 15)

18. Gain Formal Acceptance (5 Days) (Link to 14)

19. Archive Files/Documents (1 Day) (Link to 17)

20. Closeout Meeting (1 day) (Link to 19)

Assignment 2- Resources and Instructions

1. Use the Resource Sheet view in MS Project to enter the following names of personnel assigned to the project:

a. John

b. Mike

c. Nancy

d. Dave

e. Dr. Jackson

f. PMO

g. (YOUR NAME) as PM

h. Pindar

i. Emilio

j. Pam

k. Estaban

l. Craig

2. Use the Gantt Chart view to assign resources from the dropdown menu under the Resource Names field for each of the following tasks:

m. Evaluation & Recommendations - John, Mike

n. Develop Project Charter - John, Mike, Nancy, Dave

o. Sponsor Review/Approval - Dr. Jackson

p. Create Preliminary Scope Statement - Nancy

q. Determine Project Team - PMO

r. Project Team Kickoff Meeting - PM

s. Develop Project Plan - Dave, PM

t. Verify & Validate User Requirements - Pindar, Emilio, Pam

u. Design System - Pindar, Estaban

v. Procure Hardware/Software - Nancy, PMO

w. Install Preliminary System - Emilio, Estaban

x. Test Preliminary System - Pindar

y. Install Live System - Emilio, Estaban

z. User Training - Craig

aa. Audit Procurement - PMO

bb. Document Lessons Learned - PM

cc. Update Files/Records - PMO

dd. Gain Formal Acceptance - Dr. Jackson

ee. Archive Files/Documents - PMO, PM

ff. Closeout Meeting - PM

 3. Generate a Resource Overview report and save and name it by choosing File - Export - Create PDF/XPS - lastnameFirstname-REPORT1- Publish Range All (submit this file with your MS Project file).

4. Reduce the Design System by two days and allow Pindar and Estaban to work overtime to keep the schedule on track.  

5. As PM, Schedule yourself for a doctor's appointment on the final day of the project (moving it out one extra day) for the Closeout Meeting.

Assignment 3- Resources and Instructions

1. Using the Gantt Chart view, create a detailed and comprehensive timeline by taking the following steps:

a. Add an "End Project" milestone and link it to the final activity.

b. Add a "Charter Approved" milestone after the Sponsor Review/Approval activity.

c. Link the Create Preliminary Scope Statement and Determine the Project Team to the Charter Approved milestone (Hint: Use predecessor column).

d. Change the predecessors in the Project Team Kickoff Meeting activity to the two prior activities (Create Prelim Scope/Determine Project Team). 

e. Add a "Project Plan Approved" milestone and link it to the Develop Project Plan activity.

f. Link the Verify & Validate User Requirements activity to the Project Approved milestone.

g. Add a "Live Rollout" milestone after the link to User Training.

h. Link the Audit Procurement and Gain Formal Acceptance activities to the Live Rollout milestone.

2. Add the following Summary Tasks:

  • Initiation Phase - from Evaluation & Recommendation to Charter Approved milestone
  • Planning Phase - from Create Preliminary Scope to Project Plan Approved milestone
  • Execution Phase - from Verify & Validate User to Live Rollout milestone
  • Closeout Phase - from Audit Procurements to End Project milestone

3. Generate a timeline showing only the four phases above along with the milestones. 

a. Color-code each phase with a different color.  

b. Pull out the milestones from the timeline (if necessary). 

c. Create a presentation-size copy and paste it into a blank Word Document (may be helpful to use a landscape orientation). Save it, name it (lastnameTimeline), and submit this with your MS Project file.

Assignment 4- Resources and Instructions

1. Using the Gantt Chart view, take note of your current completion date for the project.

2. Set the Status Date of the project to today's date.

3. Set a Baseline for the entire project.

4. Show the baseline (gray bars) on your timeline.

5. Add the following completion percentages to the tasks below: 

a. Evaluation & Recommendation - 100% complete

b. Develop Project Charter - 95% complete

6. Move the Sponsor Review/Approval task out 2 business days (add two days) and keep the link to the next task.

7. Show the critical tasks on the timeline.

8. Adjust the Duration on critical tasks that can logically be changed to get your project back to its original completion date (cannot change Sponsor Review/Approval activity again)

9. Generate a Project Overview report by phase (default). Save and name the file: Choose File - save as - browse to where to save - from Save as type: dropdown - select PDF Files - rename lastname OVERVIEW (leave publish range set to "All").

10. Provide a Resource Overview report. Save and name the file: Choose File - save as - browse to where to save - from Save as type: dropdown - select PDF Files - rename lastname RESOURCE (leave publish range set to "All").

Assignment 5 - Resources and Instructions

1. Access the Resource View of your project.

2. Add the following Standard Rate for each of the employees or offices below (you must also enter Overtime rates for Pindar and Estaban):

a. John - $35/hr

b. Mike - $35/hr

c. Nancy - $35/hr

d. Dave - $35/hr

e. Dr. Jackson - $65/hr

f. PMO - $45/hr

g. Project Manager (student) - $40/hr

h. Pindar - $55/hr std. - $82.50/hr overtime

i. Emilio - $55/hr

j. Pam - $35/hr

k. Estaban - $55/hr std. - $82.50/hr overtime

l. Craig - $35/hr

3. Enter the following material costs to your sheet at the bottom.

a. Resource Name: Hardware - Type: Material - Material: Bundles

b. Resource Name: Software - Type: Material - Material: Flat Fee

4. Attach 3 Hardware Bundles and 1 Software Flat Fee to the Procure Hardware/Software task within the Execution phase.

5. Generate a Resource Cost Overview report. Save as a PDF file named lastnameCOST1.

6. Generate a Task Cost Overview report. Save as a PDF file named lastnameCOST2.

Attachment:- Assignment File.rar

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M92478438

Have any Question?


Related Questions in Project Management

Discuss the different approaches to developing either a

Discuss the different approaches to developing either a Product Breakdown Structure (PBS) OR a Work Breakdown Structure (WBS).

Annotated bibliographythis table lists criteria and

Annotated Bibliography This table lists criteria and criteria group name in the first column. The first row lists level names and includes scores if the rubric uses a numeric scoring method. Criteria Exemplary Competent ...

Course - project managementproject environment amp planning

Course - Project Management "Project Environment & Planning (PEP1)" Basic essay structure An essay is a piece of continuous, flowing, paragraphed text that is (usually) uninterrupted by headings, so it can appear to be u ...

Project proposal -project - plan for implementing spc for

PROJECT PROPOSAL - Project - Plan for implementing SPC for improvement Introduction/aims/objectives - 200 words max Indicative literature review - 500 words max Indicative research methodology - 500 words max An idea to ...

What are the types of documents required to define

What are the types of documents required to define parameters in a project?

Define the kano model and how it helps in gathering

Define the Kano model and how it helps in gathering customer requirements.

Developing an innovative solution to a problem involves

Developing an innovative solution to a problem involves several steps.kindly elaborate?

1 what are the limitations in a scrum-of-scrum approach2

1: What are the limitations in a scrum-of-scrum approach? 2: why are corporate culture and values so important to successfully implement an agile project management approach? 3: Can you explain the situation where we mig ...

Read the article - project management time amp cost

Read the article - Project Management Time & Cost Estimation Techniques: An Overview by Sid Kemp Using this article and other resources that you locate, write a one page paper answering the following points: - Explain wh ...

Reflect on kotters 2007 steps for establishing a strategic

Reflect on Kotter's (2007) steps for establishing a strategic vision and buy-in for change. Describe how that framework can be applied to your strategic initiatives withinproject. Provide thoughts on how this could impro ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As