A project to remodel an office area has the following activities. (Hint: You will need to build an AIB diagram, perform a forward pass, and perform a backward pass to answer this question.)

Activity                     Duration                         Predecessors

A                               4 months                                 ---

B                              3 months                                   ---

C                             3 months                                    ---

D                             5 months                                    C

E                            3 months                                   A, B

F                             3 months                                  B, C

G                           3 months                                    E, F

H                         4 months                                      D, F

I                           5 months                                        G

J                          2 months                                         H

a)      What are the critical path activities?

b)      b) What is the project's scheduled completion time?

c)       c) What is the slack or float for Activity C? Show your calculations.

d)      d) What is the slack or float for Activity D? Show your calculations.

e)      e) What is the slack or float for Activity F? Show your calculations.

f)       f) What is the slack or float for Activity G? Show your calculations.

(TCO F) Analyze and compare the costs of the two projects in terms of performance efficiency, budget, and schedule. Make sure to show your calculations and analyze and explain the results. (Note: Providing just numbers will receive only partial credit.)

Project A: The budgeted cost of work performed is $48,000, and the actual cost of work performed is $52,000. The budgeted cost of work scheduled is $54,000.

Project B: The budgeted cost of work performed is $108,000, and the actual cost of work performed is $200,000. The budgeted cost of work scheduled is $232,000.

(TCO B) Speedy Computer, Inc. (SCI) is going to introduce its first laptop computer. Although SCI recognizes that it is a late entry into the market, it believes that there is room for an inexpensive product at the low end of the market. Its design process will start with a conceptual design performed concurrently with the disassembly and analysis of a select group of the competitor's products. The best components consistent with the conceptual design will then be used as the basis for the working design. A prototype will then be developed, with a focus on using components that are readily available in the marketplace. The prototype will be tested for technical performance and ease of use, and a cost estimate will be prepared to determine if the product can be profitably manufactured.  If the prototype shows promise, work will begin on a marketing program and operations services, which include the development of user manuals and service programs. Manufacturing will be performed by subcontractors to the greatest extent possible to reduce risk. Final assembly and testing will be performed at SCI's existing facilities. 

Prepare a work breakdown structure (WBS) for this project with activities corresponding to a two-level task and subtask hierarchy. Number the WBS codes so that the level of each activity is clearly identified. Do not worry about indentation.

(TCO B) You are reaching the end of your graduate-school program, and you are planning a large party to celebrate your success! You have rented out the local forest preserve as the venue for your party. Applying your project-management skills, you want to ensure you have everything planned out, and you've asked your family and friends to be a part of your team to hold this party. At your party, you have made it clear to your team what you want to have delivered. After all, it's your party--you can have whatever you want!

Some of the key items you want at your party include:

graduation announcements;

party invitations;

live entertainment;

games (for adults and for children);

food;

beverages;

and convenience for all (parking, restroom facilities, etc.).

a) To ensure you have a clear scope for your team, create a 2-level WBS. Don't forget to include your WBS numbering. In your WBS, how many work packages have been created?

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M9530947

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As