1. Information to develop a project network is collected from the

A. Organization breakdown structure
B. Work breakdown structure
C. Budget
D. Project proposal
E. Responsibility matrix

2. Which of the following represents an activity on an AON project network?

A. An arrow
B. A line
C. A node
D. Both A and B are correct
E. A, B, and C are all correct

3. Arrows on an AON project network represent:

A. An activity
B. Project flow
C. Dependency
D. Both B and C are correct
E. Both A and B are correct

4. When translated into a project network, a work package will become

A. A single activity
B. One or more activities
C. A milestone
D. A critical path
E. An arrow

5. Which of the following is provided by a project network but not by the work breakdown structure?

A. Dependencies
B. Sequencing
C. Interrelationships
D. Both A and B are correct
E. A, B, and C are all correct

6. On a project network, the activity times are derived from the

A. Organization breakdown structure
B. Work packages
C. Budget
D. Project proposal
E. Responsibility matrix

7. Part of a project is to Develop Product Specifications. This is best classified as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

8. An activity that has more than one dependency arrow flowing into it is termed a(n)

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

9. The critical path in a project network is the

A. Shortest path through the network
B. Longest path through the network
C. Network path with the most difficult activities
D. Network path using the most resources
E. Network path with the most merge activities

10. A/an _________ activity has more than one dependency arrow flowing from it.

A. Parallel
B. Critical path
C. Burst
D. Merge
E. Independent

11. An item on a project network is Design Software Completed. This is best described as a(n)

A. Event
B. Path
C. Activity
D. Node
E. Milestone

12. Activities which can take place at the same time are termed

A. Parallel activity
B. Critical path
C. Burst activity
D. Merge activity
E. Independent activity

13. A sequence of connected, dependent activities is termed a(n)

A. Critical path
B. Parallel path
C. Activity chain
D. Path
E. Dependent chain

14. An AON project network uses which of the following basic building blocks?

A. Arrows
B. Bars
C. Nodes
D. Both A and C are correct
E. A, B, and C are all correct

15. Which of the following is not one of the basic rules to follow when developing project networks?

A. An activity cannot begin until all preceding activities have been completed
B. Each activity must have a unique identification number
C. Conditional statements are allowed but looping statements are not allowed
D. An activity identification number must be larger that that of any preceding activities
E. Networks flow from left to right

16. ________ activities must be completed immediately before a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

17. ________ activities are to be completed immediately following a particular activity.

A. Merge
B. Burst
C. Predecessor
D. Successor
E. Critical

18. The forward pass in project network calculations determines the

A. Earliest time's activities can begin
B. Earliest time's activities can be finished
C. Duration of the project
D. Both A and B are correct
E. A, B, and C are all correct

19. The backward pass in project network calculations determines the

A. Latest time's activities can begin
B. Earliest time's activities can be finished
C. Critical path
D. Both A and C are correct
E. A, B, and C are all correct

20. Which of the following correctly calculates the early finish for an activity?

A. LS + DUR
B. ES + DUR
C. LF + DUR
D. ES + SL
E. LF + SL

21. Which of the following correctly calculates the late start for an activity?

A. EF - DUR
B. ES - DUR
C. LF - DUR
D. ES - SL
E. LF - SLACK

22. The amount of time an activity can be delayed and yet not delay the project is termed

A. Total slack
B. Free slack
C. Critical float
D. Float pad
E. Slip pad

23. Which of the following will correctly calculate the total slack in an activity?

A. LS - ES
B. LF - EF
C. LS - LF
D. LF - ES
E. Both A and B are correct

24. The laying pipe example in the text illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

25. Using a special color copy machine for a tradeshow publication illustrates the concept of

A. Laddering
B. Hammock activities
C. Critical path
D. Concurrent engineering
E. Forward pass

26. If, for some reason, the project must be expedited to meet an earlier date, which of the following actions would the project manager take first?

A. Check to see which activities cost the least
B. Check to see which activities have the longest duration
C. Check to see which activities are on the critical path
D. Check to see which activities have the most slack
E. Check to see which activities have the highest risk

27. Typically an activity on a project network represents

A. A single work package
B. One or more tasks from a work package
C. Several work packages
D. A sub-deliverable
E. A cost account

28. Project network logic errors include which of the following?

A. Activities with less than 1 day duration
B. Sequences such as "if test successful build prototype, if failure redesign"
C. A sequence such as B succeeds A, C succeeds B, A succeeds C
D. Both B and C are network logic errors
E. A, B, and C are all network logic errors

29. Which company utilized concurrent engineering to design a new line of cars and in the process completed its development six months ahead of schedule?

A. General Motors
B. Chrysler
C. Ford
D. Nissan
E. Toyota

30. The minimum amount of time a dependent activity must be delayed to begin or end is referred to as:

A. Hammock
B. Laddering
C. Lag
D. Cushion
E. Buffer

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91601660
  • Price:- $30

Priced at Now at $30, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As