Ask Management Information System Expert

1. As part of a major plant renovation protect the industnal engineering department has been asked to balance a revised assembly operation to achieve an output of 240 units per eight-hour day. Task times and precedence relationship are as follows:

2022_Task time and precedence relationship.jpg

Do each of the follomng

b.  Determine the minimum cycle time the maximum cycle time and the calculated cycle time (Round your answers to 1 decimal place.)

c.  Determine the minimum number of stations needed (Round your answer to the next whole number.)

d. Assign tasks to workstations on the basis of greatest number of following tasks. Use longest processing time as a tiebreaker. If ties still exist, assume indifference in choice.

472_work stations and following tasks.jpg

e. Compute the percentage of idle time for the assignment in part d. Use the actual bottleneck cycle time in your calculation. (Round your answer to 1 decimal place. Omit the "%" sign in your response.)

2. For the set of tasks given below do the following

1857_set of tasks.jpg

b. Determine the minimum and maximum cycle times in seconds for a desired output of 500 units in a se. en-hour day /Round your answers to 1 decimal place.)

c. Determine the minimum number of mailistaticcs for output of 500 units per day (Round up your answer to the next whole number.)

d. Balance the line using the greatest positional v.sight heuristic. Break ties with the most foltowng tasks heuristic Use a cycle time of 50 seconds.

483_work stations and following tasks2.jpg

e. Calculate the percentage idle time for the line using the 50 second cycle time (Round your answer to 1 decimal place. Omit the -`14- sign in your response.)

3. A waker-machine operation was found to ineohe 3.3 minutes of machine time per cycle in the course of 40 cycles of stopwatch study The Aixker's ume averaged 2 8 minutes per cycle. and the Atrker was given a rating of 120 percent (mac hne rating is 100 percent) Midway through the study, the worker took a 10-nurxite rest freak Assuming an anowance facto( of 13 percent of A** time wench is appbed oft; to the worker element (not the machine element) determine the standard time tot this job (Do not round Intermediate calculations. Round your final answer to 2 decimal places.)

Management Information System, Management Studies

  • Category:- Management Information System
  • Reference No.:- M91908485
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Management Information System

Search the csu library the internet or any specific

Search the CSU library, the Internet, or any specific websites, and scan IT industry magazines to find an example of an IT project that had problems due to organizational issues. Write a paper summarizing the key stakeho ...

Question how can company protect the new emerging

Question : How can company protect the new emerging technology ventures from profit pressures of the parent organization (APA format required, Turntin check required . Minimum 250 words essay) How do companies overcome l ...

Communication and team decision makingpart 1 sharpening the

Communication and Team Decision Making Part 1: Sharpening the Team Mind: Communication and Collective Intelligence A. What are some of the possible biases and points of error that may arise in team communication systems? ...

Question provide an explanation of ifwherehow does active

Question : Provide an explanation of if/where/how does Active Directory support network security,14 pages (2,000-2,500) in APA format. Include abstract and conclusion. Do not include wikis, message boards, support forums ...

Question how companies could effectively use emerging

Question : How companies could effectively use emerging technology to win over its competitors. APA format required. 250 words essay required. The response must be typed, single spaced, must be in times new roman font (s ...

Question how customers could effectively use emerging

Question : How customers could effectively use emerging technology to win over its customers. APA format required. 250 words essay required. turntin check require. The response must be typed, single spaced, must be in ti ...

Part 1 - create an 8 slide powerpoint presentation on

Part 1 - Create an 8 slide PowerPoint presentation on foundational concepts specific to physical security. Part 2 - Write 4 pages detailing the framework for the design of an integrated data center. Assessment Instructio ...

In chapter 2 of the text - managing amp using information

In Chapter 2 of the text - Managing & Using Information Systems: A Strategic Approach, the chapter discusses why information systems experience failure often because of organizational strategy. A classic example of this ...

Review at least 4 articles on balanced scorecard and

Review at least 4 articles on Balanced Scorecard and complete the following activities: 1. Write annotated summary of each article. Use APA throughout. 2. As an IT professional, discuss how you will use Balanced Scorecar ...

Data resources management questionsq1 the dama dmbok

Data Resources Management QUESTIONS Q1. The DAMA DMBOK textbook describes the following two core activities as part of the Data Architecture management exercise: "Understanding enterprise information needs" and "Develop ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As