Ask Project Management Expert

1. Liquidation value of the firm's assets could be considered as________________

a. The minimum wealth of shareholder
b. The maximum wealth of shareholder
c. The average wealth of shareholder
d. None

2. If ‘P' be the initial investment, ‘I' be the interest rate and ‘T' be the time period for which funds are invested then interest earned will be______________

a. P*I/T
b. P*T/I

c. (P*I*T)2

d. P*I*T

3. Following the above given conditions, compound Interest be given by___________

a. P*(1+I)1/T
b. P*(1+I)T
c. (P*I*T)T
d. Can not be calculated

4. Firms resorting to ‘Proactive Growth'?
a. Do constant strategic planning
b. Watch things happening
c. Never plan but work on fortune
d. None

5. ‘SPACE' stands for___________________

6. Increasing marketing expenditure leading to an increased market share is known as________________
a. Market development
b. Market penetration
c. Market expansion
d. Market growth

7. If profit after tax is ‘A' ,depreciation be ‘B' and interest be ‘I' then Interest cover ratio is given by______________

8. E-V rule is also called_____________
a. Mean co variance rule
b. Mean variance rule
c. Mean deviation rule
d. None

9. In case of internally generated funds the opportunity cost to the firm is____________
a. Zero
b. The lending rate
c. The borrowing rate
d. None
10. ‘PERT' stands for__________________

Part Two:

1. Write a note on ‘Sinking Fund Payment'.

2. Differentiate between PERT and CPM Model?

3. What is ‘Capital Asset Pricing Model (CAPM)'?

4. What do you understand by PBP (Payback Period Method)?

5. Briefly explain the planning for procurement? 

Project partnering at British Airports Authority (BAA)

The construction sector in recent times has not been noted for its high levels of performance. Firms like BAA, who own and operate airports including Heathrow and Gatwick - London's two major airports - rely heavily on their suppliers, including their construction suppliers, for their own performance. Where construction projects are delayed, the financial consequences can be disastrous. Furthermore, the disciplines of working on airport premises, including the security issues, play a significant part in the daily working lives of project staff. New firms bringing new staff onto the airport sites invariably require time to bring them up to speed with the appropriate ways of working.
Particular problems include:

- Security - all personnel with access to airside parts of the airport (i.e. past passport control) must be security vetted and trained. The vetting process takes six weeks, so firms must prepare project staff in advance;

- Deliveries - getting materials into the airport is problematic, due to significant congestion and lack of availability of areas for storage;

- Constant use of terminal buildings by passengers - the closing of areas causes problems with passenger capacity. The firms are required to work with the constraints of passengers using the areas around where the work is being carried out and physical and noise intrusion must be kept to a minimum;

- The commercial activities (shops and restaurants) are the economic lifeblood of the business, with large ground-rents. The objective of projects involving these areas is not simply to complete works on time but as early as possible, so that the areas can start to generate rental incomes.

The traditional approach to managing fit-out projects (changing internal layouts to accommodate different facilities and in particular new retail facilities) was that every contract was different, and would be negotiated with different contractors. These would then employ their own sub-contractors to carry out parts of the work. The approach that has worked far better for all concerned has been through the appointment of lead contractors, with long-term contracts - in most cases 10 years - to be the prime supplier of fit-out services to B.A.A. This particular contract was awarded to MACE. As part of the agreement, BAA has paid for MACE staff to attend training programmes. This has extended further, with help being offered to their suppliers - of both materials and labour - for development. Where particular problems are identified, the supplier can be asked to take part in an improvement programme. Satisfactory completion can result in similar long-term deals (tied to continual improvement) being offered to those suppliers. In some cases the problems - particularly with designs for areas - have been the responsibility of BAA. The mechanisms are now in place to identify these problems and to introduce new practices to avoid them in future.

1) Summarise the arguments for such a policy of partnering with a major supplier such as BAA and MACE have done here.

2) Carry out further research to identify further examples of partnering in projects. How well do they appear to be working?

Caselet 2

The Big Dig

Any project that involves tunnelling is risky. Any project that involved tunneling under a city whilst trying to keep that city fully operational, is very risky. When that city is bottom in the USA, it is in a risk category all of its own. This does not, how - ever, excuse the financial performance of this project, the results of which are exceptional and even make the performance of previous ‘stars of disaster' such as the Channel Tunnel, look good. During the 1950s, the Commonwealth of Massachusetts commissioned new roads as part of a national road-building frenzy that took place at that time. The result was a partly elevated freeway that cut the city off from its old harbour and over time coped increasingly less well with the volumes of traffic that were trying to use it. For many years, the project had been the subject of much politicking and had been rejected by a number of national administrations. In 1993, it was given the go-ahead. At this time the budget was $US2.6

billion, an enormous sum of money for an 8-mile tunnel, but given the technical complexity of the task, this was considered acceptable. Gradually the costs rose, until in 1998, the estimated final cost was 410.4 billion. By mid-2000 this had risen to $13 billion and by mid-2001 to over $15 billion. It was still considered a technical success, but both politically and economically, it was a disaster. In project management terms it is also a disaster - a 500 per cent-plus overrun on budget can only be described as ‘talented'. How did such a financial disaster occur? The first is a feature of many large ‘political' projects - that the ‘real cost' would not be politically acceptable. The original budget was deliberately deflated to make the project happen. The second is technical risk - that of the tunnelling process. The ground through which the tunnelling is being carried out is reclaimed land that was originally under the sea. The tunnelling process being used was also new, presenting a degree of technical novelty.

1) How might the project be considered a technical success but an economic, political and project management disaster?

2) Suggest how the 500 per cent-plus overrun might have come about. 

1. Define the term Integration Management? And how would you explain the Project plan in detail?

2. The funds and personnel requirements of the project change significantly with the stage of its life cycle. What are the stages in the life cycle of project? Describe them.

Project Management, Management Studies

  • Category:- Project Management
  • Reference No.:- M91066321
  • Price:- $40

Priced at Now at $40, Verified Solution

Have any Question?


Related Questions in Project Management

Presentation and written assessment -the argumentative

Presentation and Written Assessment - The argumentative essay must be 1500 words in length. The presentation is about 10-15 minutes long depending on the size of the group. Task Description: The objective of this assignm ...

Topic - identifying the ways to overcome the communication

Topic - Identifying the ways to overcome the communication barriers of international project management students at central Queensland University. Literature review (1000 words) References would be needed in this section ...

Case study continuous improvementintroductionprecision

Case study: Continuous Improvement Introduction Precision Engineering Works Private Limited (PEW) is an original equipment manufacturer specialising in plastic moulding parts for the telecommunication industry. They have ...

Advanced project risk managementaimthe aim of this

Advanced Project Risk Management Aim: The aim of this assignment is to: demonstrate the understanding of Decision Tree/Expected Monetary Value and the use of the software Precision Tree schedule a project using Oracle Pr ...

Critical analysis reportthis is a group assessment for face

Critical Analysis Report This is a group assessment for face to face students and individual assessment for distance students The primary purpose of this assessment is to help you to develop and demonstrate your skills i ...

Project managment1explain what is meant by the following

Project managment 1. Explain what is meant by the following: "The project scope statement should not be built in isolation." 2. Discuss project management related problems created due to "scope creep." Each question shou ...

Project management for business assignment -enabling a

Project Management for Business Assignment - Enabling a Customer-Centric Experience through Project Management (Case Study Adapted from Project Management Institutes) Organization: Du Telecom and Huawei Technologies Co. ...

Principles of project management minor case study

Principles of Project Management Minor Case Study Assignment - Assignment objective - You are required to investigate a Project Management scenario, using information given to develop a written report and presentation to ...

Project management assessment - research studypurpose of

Project Management Assessment - Research Study Purpose of the assessment - Develop skills in Project communication planning. Communication is Key to Successful Project Management. The cases illustrate different approache ...

Assessmentthis assignment involves the portfolio of

Assessment This assignment involves the Portfolio of Materials and Team Charter 1. Description and justification of the innovation process used. A 1-page plan/outline that explains how social media will be used A short b ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As