Your project to deliver a product has five activities, each with a finish-to-start relationship. Project baseline information is presented below indicating the planned schedule and budgeted cost of each activity.

Baseline

Activity Name

% Complete

Duration

(Baseline)

Start

(Baseline)

Finish

(Baseline)

Cost

(Baseline)

Product

0

256 days

6/1/11

5/23/12

 

   Requirements

0

60 days

6/1/11

8/23/11

70,000.00

   Design

0

60 days

8/24/11

11/15/11

   85,000.00

   Build

0

90 days

11/16/11

3/20/12

100,000.00

   Test

0

45 days

3/21/12

5/22/12

60,000.00

   Release

0

0 days

5/23/12

5/23/12

0.00

You have to report project status as of January 31, 2012. The associated schedule and cost information is provided below. Assume a constant resource loading (i.e., planned expenditures are constant over the duration of each activity).

Actual

Activity Name

% Complete

Duration

(Actual)

Start

(Actual)

Finish

(Actual)

Cost

(Actual)

Product

 

215 days

6/1/11

NA

 

   Requirements

100

65 days

6/1/11

8/30/11

68,000.00

   Design

100

70 days

8/31/11

11/20/11

   85,000.00

   Build

80

80 days

11/21/11

NA

90,000.00

   Test

0

0 days

NA

NA

0.00

   Release

0

0 days

NA

NA

0.00

Calculate planned value (PV), earned value (EV), and actual cost (AC) as of January 31, 2012 and answer the questions below. Show all work. Calculate dollar values to two decimal places. Calculate all other variables to three decimal places.

1. What earned value measurement determines whether or not the project is ahead of schedule or behind schedule?What is that value?

2. What earned value measurement determines the project's rate of schedule progress? What is that value?

3. Is the project ahead of schedule, on schedule, or behind schedule? Why?

4. What earned value measurement determines how much the project is under budget or over budget? What is that value?

5. What earned value measurement is used to determine project cost efficiency. What is that value?

6. Is the project over budget, under budget, or on budget? Why?

7. Based on the current project status, what is the estimated total project cost at completion? How much more or less money (other than the current budgeted amount) will you need to finish the project?

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M91380870
  • Price:- $20

Guranteed 24 Hours Delivery, In Price:- $20

Have any Question?


Related Questions in Operation Management

1- one advantage of a is that it lsquobroadens individual

1- One advantage of a ________ is that it ‘broadens individual outlook?’ A. Professional incentive B. Individual incentive C. Benefit D. Executive incentive E. Group incentive 2- In the 1940s, a survey revealed that what ...

Discussion questions 1 what organizational conditions seem

Discussion Questions 1. What organizational conditions seem to support creative thinking at Nottingham-Spirk? Why do these conditions support creativity? 2. Explain how the converging-diverging sessions at Nottingham-Spi ...

Which one of the following best characterizes public

Which ONE of the following best characterizes Public Relations: A. Issues Driven. B. External Source of Ideation. C. Deals with uncommitted publics for the most part. D. Creates Understandings between organizations and t ...

1 in which of the following cases the use of an impersonal

1. In which of the following cases the use of an impersonal voice is most likely to be appropriate? In internal persuasive messages to emphasize shared work goals In external persuasive messages to emphasize reader benef ...

Resources the art and science of leadership ch 4 amp ch 6

Resources: The Art and Science of Leadership, Ch. 4 & Ch. 6 and Leadership Newsletter Template. Select someone in a leadership position at your organization or at a local company where you might seek employment. This ind ...

You have a job assisting the medical director at a family

You have a job assisting the Medical Director at a Family Medical Clinic in New York City. The Medical Director is concerned about the long wait times of patients visiting the clinic and would like to improve operations. ...

A discuss the difference between speculative risk and pure

a) Discuss the difference between speculative risk and pure risk. b) How can a business owner identify risk exposure? c) What are some programs that a business owner can use to reduce risk? d) Discuss two or more investm ...

1 alpha company places 10 orders per year with its supplier

1. Alpha Company places 10 orders per year with its supplier. Each order is for an amount exactly equal to the EOQ. Alpha's order cost has been determined to be $50 per order. Alpha carries no safety stock at all. What i ...

1 why has the experience curve proved to be a fundamental

1. Why has the experience curve proved to be a fundamental and very influential concept in the history of strategic management? Answer by giving a brief introdction about the the history of strategic management. Explain ...

1 correctly explains how public opinion impacts

1. Correctly explains how public opinion impacts politics/public policy. 2. Correctly defines all 4 of the main impacts of the media on public opinion (agenda-setting, framing, reinforcement and priming). 3. Provides exa ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As