You have been assigned to manage the development of an organization's first Web site. The site will be highly complex and interactive, and neither your project team nor the client has much experience with Web site development.

The timeline is extremely aggressive. And delay will be costly for both your firm and the client. You have a project sponsor and have achieved agreement and sign-off on both the project charter and the project management plan. Client personnel have been kept fully informed of the project's progress through status reports and regular meetings. The project is on schedule and within the budget, and a final perfunctory review has been scheduled. Suddenly you hear that the entire effort may be cancelled because the product developed is totally unacceptable. What is the MOST likely cause of this situation?

A. A key stakeholder was not adequately involved in the project

B. The project charter and project management plan were not thoroughly explained or adequately reviewed by the client

C. Communications arrangements were inadequate and did not provide the required information to interested parties

D. The project sponsor failed to provide adequate support for the project

Business Management, Management Studies

  • Category:- Business Management
  • Reference No.:- M91780742
  • Price:- $10

Priced at Now at $10, Verified Solution

Have any Question?


Related Questions in Business Management

Parmigiano-reggiano global recognition of geographical

Parmigiano-Reggiano: Global Recognition of Geographical Indications What historical factors have helped support the consortium's claims for the geographic specificity of Parmigiano-Reggiano and Parmesan? What are the eco ...

Consider a convenience store that is open 247 and stocks

Consider a convenience store that is open 24/7 and stocks paper towel rolls. Each roll of paper towels sells for $2.25. The paper towel vendor sells the convenience store rolls based on the quantity purchased. The purcha ...

Using a random sample of n 36 the sample mean is 292

Using a random sample of n = 36, the sample mean is 2.92. Suppose that the population standard deviation is σ=0.18. Is the above statistical evidence sufficient to make the following claim that µ

1 is corporate culture an important element in an

1. Is corporate culture an important element in an organization and its strategic direction? 2. How can organizational culture be created, influenced, and changed?

What are the supply and demand elasticities what are the

What are the supply and demand elasticities, what are the determinants of price elasticity of demand and supply, and demonstrate the relationship between elasticity and total revenue.

In class today we spoke about leadership and ways a leader

In class today we spoke about leadership and ways a leader could utilize the below list of concepts could you help me understand as a leader how I could uitlize them and an example of what they are. In the role of leader ...

Generate a c program for fibonacci function using

Generate a C++ program for Fibonacci function using Stack Fibonacci function Fib(n) is given below. Fib(n)= Fib(n-1) + Fib(n-2) for n > 1 Fib(n)= 1 for n=1 Fib(n)= 0 for n=0 Using following initialization unsigned int *F ...

Toy wooden blocks are packaged in bags of 9 one bag

Toy wooden blocks are packaged in bags of 9. One bag contains 6 maple blocks and 3 birch blocks, while a second bag contains 5 maple blocks and 4 birch blocks. One block is drawn from the first bag and placed into the se ...

Michael porter says that the essence of strategy is

Michael Porter says that" the essence of strategy is choosing what not to do." Using a company of your choice, illustrate Porter's statement.

Gas prices fluctuate often and in both directions in your

Gas prices fluctuate often and in both directions. In your initial post, respond to the following: How responsive do you think consumers will be to the price change when these fluctuations occur due to changes in supply? ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As