You are the manager of a project to improve billing process at your firm. The table below contains the data you will need to conduct a sales analysis of the project. Indirect costs are $1,600 per week, and penalty costs are $1,200 per week after Week 12.
a. What is the minimum-cost schedule for this project?
b. What is the difference in total project costs between the earliest completion time of the project using "normal" times and the minimum-cost schedule you derived in Part (a)?
Activity
|
Immediate Predecessor(s)
|
Normal Time (weeks)
|
Crash Time (weeks)
|
Normal Cost ($)
|
Crash Cost ($)
|
A
|
--
|
4
|
1
|
5,000
|
8,000
|
B
|
--
|
5
|
3
|
8,000
|
10,000
|
C
|
A
|
1
|
1
|
4,000
|
4,000
|
D
|
B
|
6
|
3
|
6,000
|
12,000
|
E
|
B, C
|
7
|
6
|
4,000
|
7,000
|
F
|
D
|
7
|
6
|
4,000
|
7,000
|