You are calculating the estimated time to completion for a project of 15 months’ duration and a budgeted cost of $350,000. Assuming the following information, calculate the Schedule Performance Index and estimated time to completion. (Figures are in thousands.)

Schedule Variances

Planned Value of Work Scheduled (PV)                    65

Earned Value (EV)                                                     58

Schedule Performance Index

Estimated Time to Completion

13.10 Suppose for Problem 9 that your PV was 75 and your EV was 80. Recalculate the SPI and estimated time to completion for the project with this new data.

Operation Management, Management Studies

  • Category:- Operation Management
  • Reference No.:- M92288699

Have any Question?


Related Questions in Operation Management

1 describe the consumer purchase decision process2

1. Describe the consumer purchase decision process. 2. Effective teachers know their content and continue to improve their own understanding within the disciplines to ensure student learning. Are there subjects or topics ...

A large sporting goods store is placing an order for

A large sporting goods store is placing an order for bicycles with its supplier. Four models can be ordered: the adult Long Trail, the adult Cityscape, the girl's Sea Sprite, and the boy's Trail Blazer. It is assumed tha ...

What qualitative factors in special order decisionsbull

What Qualitative Factors in Special Order Decisions? • Will USR expect the same selling price per unit on future orders? • Will other regular customers be upset if they discover the lower selling price to one of their co ...

1 in class we discussed collaboration tools such as email

1. In class, we discussed collaboration tools, such as email, voice communications, etc. I want you to compare 3 different applications/software within the same collaboration tool type. Describe each one to me. Tell me t ...

Key terms strategic alliances build-borrow-or-buy framework

Key terms: Strategic Alliances, Build-Borrow-or-buy Framework, Cost Leadership, Focus Cost Leadership, Blue-Ocean Strategy Your business is a tech company that sells new tech to 3 markets: U.S., Europe and Asia. Using th ...

Demand by quarter 1st- 3000 units 2nd- 4000 3rd- 4500

Demand by quarter : 1st- 3000 units, 2nd- 4000, 3rd- 4500, 4th-3500. ABC has traditionally used the hiring and firing of workers to accommodate the changes in demand for their products. However, they are considering main ...

1 what role does differing behavioral styles play in a

1. What role does differing behavioral styles play in a conflict? 2. Aggregate planning is described as a process of developing, analyzing, and maintaining a schedule of the overall operations for a supply chain. Other e ...

The life of a phone battery is normally distributed with a

The life of a phone battery is normally distributed with a mean of 1,100 days and a standard deviation of 60 days. Determine the following a. What fraction of batteries is expected to survive beyond 1,200 days b. what fr ...

We are doing an international project for a class where we

We are doing an international project for a class, where we have to choose a global product and introduce it to a foreign country, for this project we have decided to use the brand of '' Bimbo '' (the brand of bread), we ...

Assume you and 4 friends will start a business after

Assume you and 4 friends will start a business after graduation. (a) What are the 2 most important factors driving your choice of business entity? (b) Why are these the 2 factors most important to you? (c) What entity wo ...

  • 4,153,160 Questions Asked
  • 13,132 Experts
  • 2,558,936 Questions Answered

Ask Experts for help!!

Looking for Assignment Help?

Start excelling in your Courses, Get help with Assignment

Write us your full requirement for evaluation and you will receive response within 20 minutes turnaround time.

Ask Now Help with Problems, Get a Best Answer

Why might a bank avoid the use of interest rate swaps even

Why might a bank avoid the use of interest rate swaps, even when the institution is exposed to significant interest rate

Describe the difference between zero coupon bonds and

Describe the difference between zero coupon bonds and coupon bonds. Under what conditions will a coupon bond sell at a p

Compute the present value of an annuity of 880 per year

Compute the present value of an annuity of $ 880 per year for 16 years, given a discount rate of 6 percent per annum. As

Compute the present value of an 1150 payment made in ten

Compute the present value of an $1,150 payment made in ten years when the discount rate is 12 percent. (Do not round int

Compute the present value of an annuity of 699 per year

Compute the present value of an annuity of $ 699 per year for 19 years, given a discount rate of 6 percent per annum. As